CABLE INSTALLATION
WIRING PREPARATION
!CAUTION
Please read this section thoroughly before attempting to install wiring to this unit.
Be sure that the unit is not connected to any AC mains power source or UPS before installing any wiring to this unit. This should be installed by a qualified/certified electrician.
For access to terminal blocks, see diagrams on page 4.
NOTE
The 120V loads need to be balanced on the UPS output. To do this, when connecting 120V equipment to the Maintenance Bypass, start at one end of the output modules and fill in toward the other end. Load balancing must be performed with the UPStation GXT6000T - 208X and 240X. It is not required on the
POWER CABLE INSTALLATION
Refer to the chart below when selecting cables:
Power Cable and Protection Ratings
| 208V | 240V |
|
|
|
Max Input Current | 30 A | 30 A |
Input Protection | 40 A | 40 A |
Max Output Current | 30 A | 30 A |
Terminal Block Details | Max: 16 mm | 2 (6 AWG) |
Min: 2.5 mm2 (14 AWG) | ||
| Torque: 2 Nm (16 in/lb) |
NOTE
Customer must supply power cables between Maintenance Bypass and UPS, utility and load. (GMB12 models are supplied with an attached input power cord complete with
6