SECTION - 3
INSTALLATION
3.1INITIAL INSPECTION :
As soon as the power supply 1794 unit is unpacked, inspect for any damage that may have occurred during transit. Save all packing material until inspection is completed. If any damage is found, notify the carriers immediately. Our authorised representatives should also be notified.
3.2PHYSICAL CHECK :
This check should confirm that there are no broken knobs or connectors, that the cabinet and panel surfaces are free of dents and scratches and the meters are not scratched and cracked.
3.3ELECTRICAL CHECK :
The power supply unit 1794 should be checked against electrical specifications. An
3.4INSTALLATION DATA :
The power supply unit 1794 is shipped ready for bench operation. It is necessary only to connect the unit to a rated source of power (120V AC) and it is ready for operation.
3.5LOCATION :
The power supply 1794 unit is fan cooled. Sufficient space should be kept around the unit while in operation, so that unit do not remain in confined space or close to another heating source.The ambient temperature of the area around the unit should be less than 40°C.
3.6RACK MOUNTING :
The unit is in rack size and can be rack mounted in a conventional rack using standard mounting screws and the rack attachments optionally supplied.
3.7INPUT POWER REQUIREMENTS :
The power supply 1794 unit may be operated continuously from input voltage of 120V or 230V AC 47 - 63Hz power source. It is factory wired for 120V AC operation.
3