APC LX specifications CSI Static Uninterruptible System

Page 13

CSI SECTION 16611 STATIC UNINTERRUPTIBLE SYSTEM

1.Inspect equipment for signs of damage.

2.Verify installation per manufacturer s instructions.

3.Inspect cabinets for foreign objects.

4.Inspect Battery Units.

5.Inspect Power Modules.

B.Mechanical Inspection

1.Check all UPS and external service bypass panel internal power wiring connections.

2.Check all UPS and external service bypass panel terminal screws, nuts, and/or spade lugs for tightness.

C.Electrical Inspection:

1.Verify correct input and bypass voltage.

2.Verify correct UPS control wiring and terminations.

3.Verify voltage of all battery modules.

4.Verify neutral and ground conductors are properly landed.

5.Inspect external service bypass panel for proper terminations.

D.Site Testing:

1.Ensure proper system start-up.

2.Verify proper firmware control functions.

3.Verify proper firmware bypass operation.

4.Verify proper bypass switch operation.

5.Verify system set points.

6.Verify proper inverter operation and regulation circuits.

7.Simulate utility power failure.

CSI SECTION 16611 STATIC UNINTERRUPTIBLE SYSTEM

Image 13
Contents Part 1 General Summary APC Symmetra LXCSA StandardsModes of Operation Part 2 Product Design Requirements SubmittalsSystem Characteristics Environmental Input Power ConverterOutput Inverter Display and Controls Automatic BypassCSI Static Uninterruptible System CSI Static Uninterruptible System Battery Removable INPUT/OUPUT Electrical Terminal Part 3 Accessories Service Bypass Panel SBPSoftware and Connectivity Software Compatibility Remote UPS MonitoringFactory Assisted START-UP CSI Static Uninterruptible System Maintenance Contracts Manufacturer Field ServiceTraining