Installing your UPS requires six steps:

1.Position the UPS in the desired location. For rack mount units this may include installing the rails into the rack.

2.Hardwire the electrical connection on the input side (must be done by an authorized electrician).

3.Install the batteries. This 5000 VA UPS ships without the batteries installed.

4.Connect equipment to the UPS.

5.Power up the UPS.

6.Install PowerChuteUPS monitoring software and accessories.

1.Position the UPS

Placement

Install the UPS in a protected area that is free of excessive dust and has adequate air flow. Do not operate the UPS where the temperature and humidity are outside the specified limits.

Warning!

Changes or modifications to this unit not expressly approved by the party responsible for compliance

could void the warranty.

Installing Rack Mount Units

The Rack Mount UPS comes with standard 19” (46.5 cm) rack mount brackets (ears) installed. It is supplied with L channel supports. These supports must be used with this model to ease installation for a 19” rack.

Caution:

Remove the UPS before moving the rack.

Installing the UPS in a rack involves a four-step process:

1.Determine the location of the UPS in the rack.

2.Install the mounting rails in the rack.

3.Load the UPS into the rack.

4.Attach the mounting brackets to the rack. This section describes each step in detail.

Determine the Location of the UPS in the Rack

UPSs are heavy. Select a rack location sturdy enough to handle the weight. Mount the UPS at or near the bottom of the rack.

Select a rack location with adequate air flow that is free from excessive dust. Ensure that any air vents on the sides of the UPS are not blocked. Do not operate the UPS where temperature or humidity are outside the limits listed under Specifications, page 12.

990-7032A, Revision 3 7/01

2

Image 8
Contents 990-7032A, Revision 3 7/01 990-7032A, Revision 3 7/01 Replacement and Recycling of Batteries Handling SafetyElectrical Safety Page Table of Contents Page Contents How to Unpack the UPSIntroduction UnpackingInstallation PlacementInstalling Rack Mount Units Position the UPSInstall the Mounting Rails in the Rack Hardwire the Electrical Connection Load the UPS into the RackInstall the Batteries Connect Power and Equipment to the UPSConnect Power to the UPS Install PowerChute and AccessoriesInitial Startup Low Battery Warning Interval Operating Instructions Storage Replacing the Battery User Configuration Items How to Determine On-Battery Run TimeUPS battery life differs based on usage and environment Tower and 5U Rack Mount 5000 VA ModelsSpecifications Regulatory Agency Approvals Troubleshooting Service Limited WarrantyIf the UPS requires service do not return it to the dealer APC Contact InformationRacks Rack Type Hole Type Hardware Required Hardware IncludedAppendix B Transporting Your Smart-UPS