APC 3500 manual Mounting the MBP

Page 13

Mounting the MBP

APC by Schneider Electric recommends mounting the MBP to 3/4 inches plywood backing (36 in [914mm] high x 28 in [711mm] wide).

1.Attach the 3/4 inches plywood securely to the designated wall area. The wall should be strong enough to support the 120lb [54.5kg] MBP. Leave at least 18in [457mm] of space between the floor and the bottom of the plywood. Use appropriate hardware for the type of wall employed.

2.Measure and mark four (4) mounting-hole locations on the plywood backing. The locations will be in the shape of a rectangle measuring 25.94in [659mm] across and 33.86in [860mm] down.

3.Drill starter holes in each of the four marked locations.

4.At least three people are needed to lift the MBP and position it against the plywood backing. Line up the MBP’s four mounting holes with the four drilled starter holes.

5.Screw four (4) 1/4 x 1 inches hex-head lag bolts, along with four (4) 1/4 inches flat washers, into the holes. Use a 1/2 inches socket with ratchet and tighten until rigid.

25.94in [659]

1/4 x 1 in Lag Bolt (4)

1/4 in Flat Washer (4)

33.86in

[860]

Minimum 18 in [457] from floor!

Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation

9

Image 13
Contents Installation Page Contents Page Safety warnings SafetyLive maintenance precautions Product Overview FeaturesInternal components Schematic Environmental ConsiderationsOverview InstallationTools Panel board breakers  Removing the front door optionalMounting the MBP Internal cable connections Making external cable connections UPS connections Re-attaching the front door Installing Panel Board Breakers Removing fuses Appendix a Changing FusesReplacing fuses Page Page Page Page 2009 990-4198D-001