IBM X3950 M2 installation instructions Connect Scalability Cables to Scalability Ports

Page 8

IBM System x

Connect Scalability Cables to Scalability Ports

Notes

1.Route cables through hanger brackets, balancing the slack in the cables between the CMAs and the nodes and in the side of the rack.

2.Refer to the manuals to determine which ports to connect the cables to.

8

Image 8
Contents IBM System IBM System Links to System Manuals 8u needed for 2-node system Install slides into rack Install nodes onto the slides Install Enterprise Cable Management Arms onto nodes Connect Scalability Cables to Scalability Ports Install and Route Scalability Cables Recommended Method Install and Route Scalability Cables- Recommended Method Connect power and IO cables to system and route through CMA Secure the cables in the CMA Remove cable slack from CMA hanger brackets Node Cable Setup Verify Cabling Feedback