American Dryer Corp MDG30V installation manual Important Venting Reminders

Page 21

IMPORTANT VENTING REMINDERS

1.Ductwork size and installation should be done by a qualified professional.

2.The dryer must be exhausted to the outdoors.

3.Ductwork should be routed as short as possible to the outdoors with as few elbows as possible.

4.Avoid 90° turns, use 30° or 45° turns instead. Long radius turns after less resistance.

5.The size of the ductwork must be a minimum of 8-inches (20.32 cm) for short horizontal runs and 10-inches (25.4 cm) for vertical runs or long horizontal runs.

6.The inside of the ductwork should be as smooth as possible with no projections from sheet metal screws. Ducts added should overlap the duct to which it is to be connected.

7.ALL duct joints should be taped to prevent moisture and lint from escaping into the building.

8.Inspection or clean out doors should be installed at strategic points in the ductwork for periodic inspection and cleaning.

9.Wherever the ductwork passes through combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be centered within this opening.

10.The outside of the ductwork must be protected from the weather. A 90° elbow must be used for horizontal run and when vertically through a roof by using a 180° turn to point the opening downward. The distance between the exhaust duct and the nearest obstruction (i.e., roof or ground) must be twice the diameter of the duct.

11.DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

12.Exhaust back pressure measured by a manometer at the dryer exhaust duct area must be no less than 0 and must not exceed 0.3 inches (0.74 mb) of water column (W.C.).

13.Exhaust ductwork outlets should not be located in an area directly where make-up air openings are located.

WARNING: DRYER MUST NEVER BE OPERATED WITHOUT THE LINT FILTER/ SCREEN IN PLACE, EVEN IFAN EXTERNAL LINT COLLECTION SYSTEM IS USED.

17

Image 21
Contents MDG30V Important Note to Purchaser Retain This Manual In a Safe Place For Future ReferenceFor Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement Receiving and Handling Important InformationExplosion could Result Safety PrecautionsPage Specifications SpecificationsMDG30V UNPACKING/SETTING UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. C Important Venting Reminders Electrical Requirements Electrical InformationMust be Provided Single-Phase 1ø Wiring Connections/HookupSINGLE-PHASE 1Ø Electrical Connection Leads Important a Circuit Servicing Each Dryer Must be Provided MDG30V GAS Service Wire Approx Circuit Phase AMP Draw Voltage BreakerGAS Information Type of GAS Page Page Preparation for OPERATION/START-UP GAS Models only Preoperational TestsCoin Models Preoperational InstructionsPage OPL Models Shut Down Instructions SERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Routine Maintenance CleaningSuggested Cleaning Schedule Lubrication AdjustmentsLint Drawer Removal Standards TroubleshootingBlower motor is not operating does not start Microprocessor controller computer display reads dSFL GAS Models only Dryer operates but is taking too long to dry Excessive noise and/or vibration Data Label Data Label InformationSerial Number Procedure for Functional Check Replacement Components Page 113365 1 04/22/02-25