American Dryer Corp ML-96D installation manual Preparation for OPERATION/START-UP

Page 29

Consistent gas pressure is essential at ALL gas connections. It is recommended that a 1-inch (2.54 cm) pipe gas loop be installed in the supply line servicing a bank of dryers. An in-line pressure regulator must be installed in the gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches (29.9 mb) of water column (W.C.) pressure.

NOTE: A water column test pressure of 3.5 inches (8.7 mb) for natural gas and 10.5 inches (26.1 mb) for liquid propane (L.P.) dryers is required at the gas valve pressure tap of each dryer for proper and safe operation.

A 1/8" N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural gas and L.P. gas must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid detergent works well).

WARNING: NEVER TEST FOR LEAKS WITH A FLAME!!!

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (L.P. Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance BTUs being supplied.

IMPORTANT: The dryer and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing its individual manual shutoff valve during any pressure test of the gas supply system at test pressures equal to or less than 1/2 psig (3.5 kPa).

H. PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

1.Read ALL "CAUTION," "WARNING," and "DIRECTION" labels attached to the dryer.

2.Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label affixed to the left side panel/wall area behind the control door. In the case of 208 VAC or 240 VAC, THE SUPPLY VOLTAGE MUST MATCH THE ELECTRIC SERVICE EXACTLY .

3.Check to assure that the dryer is connected to the type of heat or gas indicated on the dryer data label.

4.The sail switch damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to assure that this important safety control is functioning.

5.Be sure that ALL gas shutoff valves are in the open position.

25

Image 29
Contents ML-96D Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement Important Information SectionWhat to do if YOU Smell GAS Safety PrecautionsPage Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Component Identification Page Location Requirements Installation ProceduresUNPACKING/SETTING UP Page Dryer Enclosure Requirements Fresh AIR Supply Create a Potential Fire Hazard Exhaust RequirementsAnywhere Downstream of Dryer Page Page Electrical Information G 9 6 D Electrical Connections GAS Information BTU Page Preparation for OPERATION/START-UP Preoperational Tests Basket Coating Operating InstructionsShut Down Instructions Parts SERVICE/PARTS InformationService Returning Warranty Cards Warranty InformationWarranty Returning Warranty PartsPage Cleaning Routine MaintenanceLubrication AdjustmentsProcedure for Functional Check Replacement Components Page Data Label Data LABEL/LOCATION InformationSerial Number For Phase 6 Models Manual Reset HI-LIMIT InstructionsADC 02/16/00-10 12/08/00-10 03/09/01-25