IMPORTANT: For extended ductwork runs, the cross section area of the duct can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 20 feet (6.09 meters) more than the original limitations of 20 feet (6.09 meters) with two (2) elbows. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, venting, and air conditioning (HVAC) firm should be consulted for proper venting information.

ALL ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be centered within this opening.

a.Outside Ductwork Protection

1)To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the exhaust ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and nearest obstruction.

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

3.Multiple Dryer (Common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a “common main duct.” The individual ducts should enter the bottom or side of the main duct at an angle not more than 45° in the direction of airflow and should be spaced at least 48-3/8 inches (122.87 cm) apart. The main duct should be tapered, with the diameter increasing before each individual 14-inch (35.56 cm) minimum for gas dryers or electric dryers, or 16-inch (40.64 cm) minimum for steam dryers (duct is added).

IMPORTANT: The dryer is not provided with a back draft damper. When exhausted into

a multiple (common) exhaust line, a back draft damper must be installed at each dryer duct.

IMPORTANT: No more than four (4) dryers should be connected to one (1) main common duct.

19

Image 23
Contents ML-130 Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Routine Maintenance Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsStandards Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Component Identification Page Location Requirements Installation ProceduresUNPACKING/SETTING UP Page This Exhaust Duct Transition Piece Must be Installed First Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Page Downstream of Dryer Page Page Page Electrical Information ML-130 II Reversing, 3ø GAS ML-130 II Reversing, 3ø Steam MLE-130 II 72 Kw Electric Reversing, 3ø MLE-130 II 80 Kw Electric Reversing, 3ø Page Page GAS Information Type of GAS Page Page Steam Information Operating Steam PressurePage Bars Page Preparation for Operation Preoperational Tests Basket Coating Operating Instructions Shut Down InstructionsPage Parts SERVICE/PARTS InformationService Returning Warranty Parts Warranty InformationReturning Warranty Cards WarrantyPage Suggested Cleaning Schedule Routine MaintenanceCleaning Steam Dryers Lubrication AdjustmentsData Label Data Label InformationSerial Number Timing Legend Reversing Timer SPIN/DWELL AdjustmentsProcedure for Functional Check Replacement Components Page Page P O R T a N T For Timer or Phase 5 Without Heat Fault ADC 113314 1- 06/21/01-25