Intel SC5300 BRP, SC5300 LX manual Inserting Power Distribution Board in Power Supply Cage

Page 73

Maintaining Your Server

8.Insert the new Power Distribution Board into the power supply cage (letter “A”). Try to route the power cables to the appropriate area at the time of insertion (see Steps 9 and 10). Do not secure the Power Distribution Board yet.

A

TP01996

Note: Cables on back of Power Distribution Board not shown to clarify insertion process.

Figure 64. Inserting Power Distribution Board in Power Supply Cage

9.Route the P1, P2, and P14 power cables to the server board and connect to appropriate connectors. Refer to the Intel® Server Board Quick Start User’s Guide or User Guide for the location of power connectors.

10.Route the longest power cables (P8, P9, P10, and P11) to the six-drive bay and connect power cables to any installed devices. Route the shorter cables (P3, P4, and P5) to the upper device bay and connect to any installed devices. Route the P6 and P7 cables to the four-drive bay and connect to any installed devices. Route the SATA drive power cables to which ever drive bay is using SATA fixed drives.

Intel® Server Chassis SC5300 User Guide

55

Image 73
Contents Order Number C51486-003 Intel Server Chassis SC5300 User Guide Manual Organization PrefaceAdditional Information and Software Safety Information Safety Cautions Intel Server Chassis SC5300 User Guide Vii Wichtige Sicherheitshinweise 重要安全指导 Consignes de sécurité Instrucciones de seguridad importantes Xii Intel Server Chassis SC5300 User Guide Xiii Xiv Contents Equipment Log and Worksheets Figures Tables Feature Summary Kit ContentsChassis Description Intel Server Chassis SC5300 Base Front View Chassis Front View SC5300 BaseIntel Server Chassis SC5300 LX Front View Chassis Front View SC5300 LX with Hot Swap ComponentsPedestal Controls and Indicators Front Panel Controls and IndicatorsFront Panel LED Descriptions Intel Server Chassis SC5300 Base Chassis Rear View Base Chassis Rear ViewBase Redundant Power and SC5300 LX Chassis Rear View Chassis Side View PeripheralsHalf-height Peripheral Bays Standard and Optional Hot Swap Drive BaysAccessories and Order Codes Accessories and Order CodesInstallation Safety Instructions Setting Up the ChassisSafety Before You Remove the Access Cover Tools and Supplies NeededSetting Up the Chassis Removing the Access Cover Remove Primary Access CoverRemoving Bezel Assembly Remove Bezel AssemblyRemoving Air Ducts Remove Air DuctsRemoving Hot Swap Fans Remove Hot Swap FansRemoving PCI Add-in Card Retainer Route Power and Data Cables to the Fixed DrivesRouting Power Cables to Fixed Drives Routing SCSI/SATA Data Cables Install 3.5-inch Floppy DriveInstalling Slides on 3.5-in Floppy Drive Installing a DVD or CD-ROM Drive Install DVD or CD-ROM DriveRemoving Six-drive Fixed Drive Cage from Chassis Install Fixed Hard DrivesOpen the lower door Installing Device Slides to Hard Drive Close the lower door of drive cage Releasing Drive Carrier from Hot Swap Cage Install Hot Swap DrivesInserting Drive Carrier into Drive Cage Install Hot Swap FansInstall Air Dam Install Server BoardConnect Cables to Server Board Securing Cables in Chassis with a Hot Swap Power SupplyRemove PCI Add-in Card Retainer Install Add-in BoardsPreparing the Chassis for a PCI Add-in Board Repeat until all PCI add-in cards are installed Reinstall the PCI Add-in Card Retainer Removing Inner Plastic Air Baffle from Processor Air Duct Install Air DuctsInstalling Air Ducts Removing Power Supply Filler Panel Install an Additional Hot Swap Power Supply ModuleInstalling Bezel Assembly Install Bezel Assembly Pedestal OnlyInstalling the Access Cover Install Primary Access CoverSetting Up the Chassis Maintaining Your Server Safety Before You Remove the Access CoversMaintaining Your Server Removing a Fixed Fan Replacing a Fixed Fan For Base and BRP Chassis OnlyRemoving a Hot Swap Fan Replacing a Hot Swap FanRemoving the Front Panel Board Replacing the Front Panel BoardInstalling the Front Panel Board Replacing a Fixed Power SupplyRemoving Fixed Power Supply Removing a Hot Swap Power Supply Replacing a Hot Swap Power SupplyRemoving Hot Swap Power Supply Replacing a Power Distribution BoardRemoving Center Divider Removing Power Distribution Board Securing Power Distribution Board to Power Supply Cage Reinstalling Center Divider Removing Fixed Power Supply Releasing Center Divider from Power Supply Cage Removing Center Divider from Power Supply Cage Inserting Power Distribution Board in Power Supply Cage TP01997 Reinstalling Hot Swap Power Supply Maintaining Your Server Single Power Supply Input Voltages Power Supply SpecificationsSingle Power Supply Output Voltages Technical Reference+3.3 24 a +5.0 +5 V Standby +12.0 48 a Environmental Specifications System Environmental SpecificationsEquipment Log Equipment Log and WorksheetsEquipment Log Current Usage Calculating Power UsageWorksheet, Total Combined Power Used by the Server Regulatory and Compliance Information Product Safety ComplianceProduct Regulatory Compliance Product EMC Compliance Class a ComplianceProduct Regulatory Compliance Markings Certifications / Registrations / DeclarationsFCC USA Electromagnetic Compatibility NoticesEurope CE Declaration of Conformity Industry Canada ICES-003Bsmi Taiwan Vcci JapanKorean RRL Compliance Regulated Specified Components World Wide Web Telephone Getting HelpMiami Limited Warranty for Intel Chassis Subassembly Products WarrantyExtent of Limited Warranty Limitations of Liability Warranty Limitations and ExclusionsTelephone Support How to Obtain Warranty ServiceReturning a Defective Product