Hearth and Home Technologies BIR50 operating instructions Chase Top, Termination Cap

Page 20

North Star

EPA Certified Fireplace

2. Chase Top

NEED NEW DRAWING

Construct a chase of desired materials main- taining a minimum 2” air space around the chimney.

3.Termination Cap

a.Install the chimney sections up through the chase enclosure. When using a TR344 round termination cap, the uppermost top section of pipe must extend 6” above the top of the chase collar to allow installation of the storm collar and termination cap. See Figure 20B.

b.For installations utilizing a TR342 telescop- ing round termination cap, the uppermost chimney section must be below the top of the chase top, but not more than 14-1/2” below the top of the chase top flashing collar. See Figure 20C.

c.For installations utilizing an ST375 square termination cap the last chimney section must not be more than 4-1/2” below the chase top. See Figure 20D.

d.For installation utilizing a TS345/TS345P Square Termination Cap, the uppermost chimney section must not be more than 3” below the chase top. See Figure 20E.

e.Attach the chase top (CT35) to the top of the chase.

f.Install the termination cap, following the instructions provided with it.

Storm Collar

Chase Flashing

2" min

6" min

2" min

Figure 20B - Installing a

TR344 Round Termination

Cap

 

 

 

 

Chase

2" min from

Top of pipe

 

 

chase top to

 

 

flashing

 

 

 

 

top of chase

 

 

 

 

 

Cap

 

 

 

 

flashing

 

 

 

 

 

 

 

 

 

 

standoff

 

 

 

4-1/2"

 

 

 

 

 

 

 

 

 

 

 

max

 

 

 

 

 

 

Figure 20D - Installing an

ST375 Square Termination

Cap

Storm Collar

Chase Flashing

2" min

14-1/2" max

Top of uppermost

chimney section

Figure 20C - Installing a

TR342 Round Telescoping

Termination Cap

Top of pipe

2" min from chase top to

 

top of chase flashing

Chase

3" max

flashing

Figure 20E - Installing

a TS345/TS345P Square

Termination Cap

ROUND TERMINATION CAP

(TR342/TR344)

METAL CHASE TOP

FIRESTOP

SPACER

FALSE

CEILING

WARNING!

Never install a single wall slip section or smoke- pipe in a chase structure. The higher temperature of this single wall pipe may radiate sufficient heat to combustible chase materials to cause a fire.

WARNING!

Detailed instructions for installation of the chase top, storm collar and termination cap are packaged with these parts. To avoid danger of fire, all instructions must be strictly followed, including the provision of air space clearance between chimney system and enclosure.To protect against the effects of corrosion on those parts exposed to the weather, we recommend that the chase top be painted with a rust-resistant paint.

Figure 20A - Chase Assembly

480-1081

20

4-03

Image 20
Contents Installation & Operating Instructions Hearth & Home TechnologiesKensington Blvd Lakeville, MNTable of Contents Safety PrecautionsListings and Code Approvals Description of the Fireplace SystemFireplace system consists of the following Required Components IncludeInstallation and Draft Considerations Outside AIR KIT InstallationHearth Extension / Floor Protection Fireplace and Hearth Extension are flush on the floorChimney Components Catalog No DescriptionCatalog No 27-3/815-3/4 PRE-INSTALLATION Preparation Fireplace Locations and Space RequirementsFraming the Fireplace Electrical Access and Wiring DiagramChimney Requirements Using Offsets and Returns Offset ChartNumber of Sections Required Dimensions reflect effective heightChimney Height Requirements above roof line Installation of Fireplace Positioning the FireplacePlacing the Protective Metal Hearth Strips Leveling the FireplaceInstalling Firestop Spacers Double-checking the Chimney AssemblyInstalling the Firestop Spacer Installing an Attic Insulation ShieldMobile home installation SL-300 Series MH842 Celing/Roof ThimbleSL-300 MH842 Celing/Roof Thimble Cont’d Securing the Chimney SystemMarking the Exit Point of the Roof Cutting out the Hole in the RoofHearth Extension Installing the Roof FlashingCompletion of the Enclosure Alternate materials worksheet Position the Hearth ExtensionConstructing a Chase Finishing MaterialMantel MaterialsChase Top Termination CapGeneral Information Outside Air Burning Process Air ControlAutomatic Combustion Control Kindling or 1st stageBurning Guidelines Fan Operating InstructionsHeat Zone Operating Instructions BTU / Hr Slide ControlOpacity Starting a FireBurn Rates Seasoning Moisture contentWood Fuel Hardwood vs. Softwood Draft Problems Storing WoodMaintenance Instructions Care and Cleaning of Glass Glass Replacement Care and Cleaning of Plated SurfacesFirebrick Replacement Brick PatternFan Replacement Fan Cord LocationBaffle Removal & Installation Door & Door GasketDoor Assembly Fascia Assembly Exploded ViewService Parts List Index Lifetime Warranty Please Return