Desa (V)K36EP, (V)K36EN Model BKT Installation, Attaching Speed Control to Firebox

Page 17

FIREPLACE INSTALLATION

Installing Optional Blower Accessory (Cont.)

17

FIREPLACE INSTALLATION

Continued

4.Be certain that all wire terminals are securely attached to ter- minals on blower motor and that the screw retaining the green ground wire is tight.

5.Mount speed control box to switch bracket by placing the plastic control shaft forward through the opening in the switch bracket (see Figure 26).

6.While supporting speed control, secure control shaft with lock nut by pushing and turning lock nut with pliers clockwise until it is tight against front panel. Place control knob provided on shaft.

7.Turn on power to duplex outlet if previously turned off per the warning in column 2, page 16.

8.Plug in blower power cord.

a.If your firebox is installed as a freestanding unit with an accessory mantel, determine whether the power cord will exit the left side or the right side of the firebox. Route power cord through exit hole and plug the power cord into a wall receptacle near the firebox.

b.If your firebox installation is recessed and/or pre-wired, plug the power cord into the duplex outlet provided. Refer to your firebox owner’s manual for instructions on wiring the duplex outlet.

CAUTION: Never touch the blower wheel while in operation.

9.Check to make sure that the power cord is completely clear of the blower wheel and that there are no other foreign objects in blower wheel. Turn blower on and check for operation. Turn blower off by turning knob fully counterclockwise before continuing.

10.Peel off the backing paper and stick the supplied wiring dia- gram decal on the firebox bottom approximately 12" in front of the blower (see Figure 27).

Switch

Speed Control

Bracket

Blower

 

 

Plug-In

Control

Knob

Locknut

Control

Duplex Outlet

 

Shaft

 

(Located underneath

 

 

 

 

firebox floor against

 

 

lower right outside wall)

Figure 26 - Attaching Speed Control to Firebox

Wiring Diagram Decal

12" in Front of Blower

Figure 27 - Location of Wiring Diagram Decal (Model May Vary From Illustration)

Model BKT Installation

Note: When installing the BKT thermostatically-controlled blower, you must first secure the thermal switch bracket to the blower if it has not already been factory installed.

1.Place the green ground wire with ring terminal between the bottom hole on the thermal switch bracket and the top ear hole on the blower assembly. Insert the phillips screw into all three pieces and tighten securely (see Figure 28).

2.Connect wire harness and power cord terminals. Connect the blue jumper wire to the blower motor terminal and the right side terminal of the thermal switch. Connect the black wire to the left side of the thermal switch and the white wire to the other remaining blower motor terminal.

Note: The power cord outer insulation sleeve may have to be stripped slightly to allow enough wire length to reach and make all connections. DO NOT trim excessive length away. Just enable enough to make all connections securely.

Power Cord

White Wire

Blue Wire Magnetic

Thermal

Strips

Switch

Air Flow

Bracket

Black

Direction

 

Wire

 

Phillips

 

Screw

 

Thermal Switch

Ring Terminal

on Green Wire

 

Air Flow Direction

 

Magnets

Route BKT

 

Blower Through

Thermodisc

This Area

 

Side View Firebox Bottom

Blower

Location

Figure 28 - Blower Model BKT

 

For morevisit www..com

111924-01B

Image 17
Contents For Your Safety What to do if YOU Smell GAS OWNER’S Operation Installation ManualFor Your Safety Safety Information Table of ContentsLocal Codes Product IdentificationLocation and Space Requirements Product FeaturesPRE-INSTALLATION Preparation Framing and Finishing ClearancesBalcony with Perpendicular Side Wall Location of Termination CAPInstallation Precautions Venting Installation InstructionsHorizontal Termination Installation Installation PlanningInstalling Siding Standoff Combustible Exterior Vertical V Horizontal H Horizontal Termination ConfigurationsCorner Installation Venting with Two 90 Elbows Horizontal System Installation Using TWO ElbowsFlat Ceiling Installation Installation for Vertical TerminationVenting with One 90 Elbow Vertical Termination ConfigurationsVertical Venting High Altitude InstallationInstalling Optional Blower Accessory Fireplace InstallationModel BK Installation Check GAS TypeAttaching Speed Control to Firebox Model BKT InstallationInstallation Items Needed Installing GAS Piping to Fireplace LocationBlower Wiring Diagram Installation Items Needed Connecting Fireplace to GAS SupplyPressure Testing Gas Supply Piping System Checking GAS ConnectionsRemoving Louver Panels Pressure Testing Fireplace Gas ConnectionsREMOVING/REPLACING Glass Door Removing Glass Door Cleaning Glass DoorWall Switch Installation Installing LOGS, Lava Rock and Glowing EmbersOptional Remote Control Wiring DiagramOperating Fireplace For Your Safety Read Before LightingLighting Instructions To Turn OFF GAS To AppliancePilot Assembly Operating Optional Blower AccessoryInspecting Burners Burner Flame PatternGlass Door Cleaning MaintenancePilot and Burners LogsObserved Problem Possible Cause Remedy TroubleshootingTop Gas leak. See Warning statement atService Hints Replacement PartsTechnical Service SpecificationsModels Illustrated Parts BreakdownKEY Part Number Description QTY Parts ListBurner Assembly for Models VK36EN, VK36ENH, VK36EP, VK36EPH Parts List Accessories Owners Registration Form Postage Required 111924-01B Warranty Information