INSTALLATION (NEW CONSTRUCTION) CONTINUED

7.Refer to wiring diagram on page 5.

Follow all the local electrical safety codes as well as the National Electrical Code (NEC).

Using UL approved wire nuts, connect house power wires to ventilating fan wires. (Fig.5)

CAUTION

Mount junction box cover carefully so that lead wires are not pinched.

8.Insert fan body and slide into adaptor assy with some strength, untill the flange overlaps the Flex-Z FastTM bracket. Secure the fan body to Flex-Z FastTM bracket by using 2 self-drilling screws, plug connector to receptacle and secure the fan body to adaptor by using machine screw (M4X6). (Fig.6)

CAUTION

Secure machine screw (M4X6) to the suitable hole and not touch the Flex-Z FastTM bracket. Please fix the screw carefully to avoid screw slip teeth.

9.Finish ceiling work. Ceiling hole should be aligned with the inside edge of the flange. (Fig.7)

10.Remove the tapes from louver and springs before installation. Remove screw (M4X8) and light cover. (Fig.8)

IMPORTANT:

Replace the sensor cover before the installation (only for plug-in Motion sensor module FV-MSVK1). As shown below:

Keep on pressing the clasps when removing the ornamental cover.

Gloves

Ornamental cover

Insert the sensor cover (attachment for FV-MSVK1) into slot.

Sensor cover

11.Install the LED lamps. (Fig.9)

12.Install light cover. (Fig.10)

13.Insert the grille mounting spring on the wiring side into the slot and insert the plug connector into the housing of the lighting unit. (Fig.11 of page 10)

FV-05-11VKSL1

 

 

Conduit

FV-05-11VKL1

 

 

 

FV-11-15VKL1

 

 

Earth ground to green

 

 

 

 

 

 

 

 

 

 

Wire nut

Junction

 

 

Live to black

box

 

 

(Fan)

 

 

 

 

Netural to

 

 

Netural to white

white

 

 

 

Two red wires (Connect

 

 

 

 

 

 

 

Live to black

 

to a general manual

 

wall switch)

Fig.5

(Light)

 

 

 

Joist

 

 

 

Plug connector

 

 

 

 

Machine

 

 

 

screw

 

 

 

(M4X6)

 

 

Receptacle

2 Self-drilling

 

screws

 

Fig.6

 

 

(270)

Ceiling

Unit: inches (mm)

10

 

 

 

 

After finishing the ceiling job, fill gap between flange and ceillng with caulk or other sealant to prevent air

leakage

Fig.7

Remove screw (M4X8)

Tapes

Light cover

Fig.8

LED lamp

Fig.9

 

Secure

 

screw

 

(M4X8)

Light cover

Fig.10

9

Image 9
Contents Installation Instructions For Your Safety General Safety InformationFig. B Please Read Prior to Installing this FANUnpacking DescriptionSupplied Accessories DimensionsWiring Diagram Air volume type CFM Factory setting FeatureDelay Time min Indication Plug ‘N Play Function DevicesTurns the fan on for 20 minutes when either Motion Plug ‘N Play Function DevicesMotion or excess humidity is detected Installation Plug ‘N Play Function Devices Installation NEW ConstructionRemove the connector cover from position , 2 or Gloves Ornamental cover Follow the to 16 on page 9 to Installation RetrofitMaintenance Replacement of Lamp Maintenance CleaningSpecifications Practical Guide to InstallationProduct Service Specifications for Base Model fans