Kohler K1191-R manual Make the Electrical Connections, Test Run the Bath, Test the Control Switch

Page 9

System Control

Chromatherapy Light Control

("On/Off")

 

Line 1 (Black)

Junction Box

Black

Ground (Green)

 

Electrician to

Green

 

provide suitable

 

strain relief

 

Line 2 (Black)

Black

 

Bonding Lugs Follow Local Codes

8. Make the Electrical Connections

NOTE: The product model number is printed on a label on the pump side of the unit. This label also identi®es the electrical rating of the product.

WARNING: Risk of electrical shock.Make sure the power has been disconnected before performing the following procedures. Refer to IMPORTANT INFORMATION section.

CAUTION: Risk of electrical shock. All services must have a Class A Ground-Fault Circuit-Interrupter (GFCI) which will provide additional protection against line-to-ground shock hazard. A dedicated service is required for the over¯owing bath.

The over¯owing bath control and system have been prewired at the factory using 220V hardwire. A licensed electrician should make a routine service connection to the junction box located on the control box.

Connect service to the junction box. The junction box contains black and green wires. The grounding conductor must not be connected to any current-carrying conductor.

Follow local electrical codes.

9. Test Run the Bath

Check the Connections and Fill the Unit

NOTE: The system will purge air at start-up. This is normal.

Check all electrical connections, and make sure the electrical power to the unit is turned on.

Make sure union connections to the pump and in-line heater are securely handtightened.

Make sure the bathing well and over¯ow channel are clean and free of debris.

Fill the bath as you would a normal bath, 4º (10.2cm) ± 6º (15.2cm) from the top, to allow for water displacement when you enter the bathing well. Water entering the over¯ow channel will ¯ow into the drain.

Test the Control Switch

Press the ″On/Off″ control switch to start the pump/motor and begin the hydro-therapy cycle. A green light in the ″On/Off″ control switch will turn on to indicate the start of the operating mode. As the pump/motor turns on and water begins to circulate, the light remain green while the unit is running.

With the unit running, check all harness (piping) connections for leaks.

Visually observe the effervescence rising to the surface of the water.

Kohler Co.

9

1012493-2-A

Image 9
Contents Installation Guide Connections and Service Access Factory-Assembled FeaturesImportant Product Information Product Notices Product InspectionTable of Contents Recommended Tools and Materials Thank You For Choosing Kohler CompanyIntroduction Before You BeginList of New Terms Roughing In Information PUMP/CONTROL AccessInstall the Rough Plumbing Construct the Stud FramingPrepare the Unit Position the Unit Install the PlumbingMake the Electrical Connections Test the Control SwitchTest Run the Bath Check the Connections and Fill the UnitTest Run the Bath Install the Faucet Trim Clean-Up After InstallationComplete the Finished Wall or Deck Using Your Bath Fill the BathOperating Sequence Chromatherapy Light Operation 1012493-2-A Kohler Co Kohler Co 1012493-2-A USA 1-800-4-KOHLER México Canada Kohler.com