AUXILIARY POWER WHILE WELDING

Simultaneous welding and power loads are permitted by following Table I. The permissible currents shown assume that current is being drawn from either the 120V or 240V supply (not both at the same time). Also, the “Output Control” is set at “10” for maximum auxiliary power.

TABLE I

SIMULTANEOUS WELDING AND POWER***

Output Selector

Permissible Power

Permissible Auxiliary

 

Setting

Watts (Unity Power

Current in Amperes

 

Factor)

@ 120V *-or- @ 240V

 

 

 

 

 

Max. Stick or Wire

 

 

 

 

Feed Setting

None

0

0

 

 

 

 

 

 

145 Stick Setting

4500

38

23

 

 

 

 

 

 

90 Stick Setting

6500

54**

27

 

 

 

 

 

 

NO WELDING

9500

80**

40

 

 

 

 

 

 

*Each duplex receptacle is limited to 20 amps.

**Not to exceed 40A per 120VAC branch circuit when

splitting the 240 VAC output.

***Use of 3-Phase AC poower is not recommended while welding.

STANDBY POWER CONNECTIONS

The RANGER 3 PHASE is suitable for temporary, standby, or emergency power using the engine manu- facturer’s recommended maintenance schedule.

The RANGER 3 PHASE can be permanently installed as a standby power unit for 240V-3 wire, single phase 40 ampere service.

WARNING

(Connections must be made by a licensed electri- cian who can determine how the 120/240V power can be adapted to the particular installation and comply with all applicable electrical codes.) The following information can be used as a guide by the electrician for most applications (refer also to the connection diagram shown in Figure 1.)

-------------------------------------------------------------------------

1.Install a double pole, double throw switch between the power company meter and the premises dis- connect.

Switch rating must be the same or greater than the customer’s premises disconnect and service over- current protection.

2.Take necessary steps to assure load is limited to the capacity of the RANGER 3 PHASE by installing a 40 amp 240V double pole circuit breaker. Maximum rated load for the 240V auxiliary is 40 amperes. Loading above 40 amperes will reduce output voltage below the allowable -10% of rated voltage which may damage appliances or other motor-driven equipment.

3.Install a 50 amp 120/240V plug (NEMA type 14-50) to the Double Pole Circuit Breaker using No. 8, 4 conductor cable of the desired length. (The 50 amp 120/240V plug is available in the optional plug kit.)

4.Plug this cable into the 50 amp 120/240V recepta- cle on the RANGER 3 PHASE case front.

RANGER 3 PHASE

Image 15
Contents Ranger Phase California Proposition 65 Warnings SafetyElectric Shock can kill Iii Welding Sparks can cause fire or explosionSûreté Pour Soudage a L’Arc Précautions DE SûretéThank You Table of Contents Ranger 3 Phase InstallationTechnical Specifications Ranger 3 Phase K2337-1 Height Width Depth WeightTowing Safety PrecautionsMachine Grounding Spark ArresterPRE-OPERATION Service High Altitude Operation Connection of Lincoln Electric Wire FeedersAngle of Operation LiftingWelder Operation Additional Safety PrecautionsAuxiliary Power InstructionsGfci Duplex Receptacles Volt 3 Phase Receptacle with GroundGround Wire Ranger 3 Phase Extension Cord Length RecommendationsType Common Electrical Devices Possible Concerns Electrical Device USE with the Ranger 3 PhaseAuxiliary Power While Welding Simultaneous Welding and PowerStandby Power Connections Connection of Ranger 3 Phase to Premises Wiring Welder Controls Function and Operation Engine SwitchOperation General DescriptionRanger 3 Phase Approximate Fuel Consumption Polarity SwitchTIG Constant Current Welding Wire Feed Welding Processes Constant VoltageWelding Process Stick Constant Current WeldingStick Auto Stopping the Engine STARTING/SHUTDOWN InstructionsBREAK-IN Period Starting the EngineK1745-1 GAS Cylinder Holder AccessoriesTIG Wire FeedRecommended Equipment StickEngine OIL Change MaintenanceSafety Precautions Routine Maintenance Engine OIL Refill CapacitiesAIR Cleaner and Other Maintenance Gfci Receptacle Testing and RESET- Ting ProcedureOIL Filter Change Engine Adjustments HOW to USE Troubleshooting Guide TroubleshootingYour local Lincoln Authorized Field Service Facility Troubleshooting Ranger 3 Phase DiagramsEngine Welder M20397 Ranger 3 Phase Precaucion Warnung