Outback Power Systems GFX1448E, GFX1424E, GFX1312E installation manual Three-Phase Stacking

Page 32

Installation

Three-Phase Stacking

In three-phase stacking, inverters are stacked to create three separate 230 Vac output legs in a wye configuration.

The output of each inverter is 120° out of phase from the others. Any two outputs produce 400 Vac between them. The outputs can be used to power three-phase loads when all inverters work together.

Only three inverters, one per phase, may be installed in a three-phase arrangement.

1.3 kVA 230 Vac

1.3 kVA

 

230 Vac

1.3 kVA 230 Vac

1.3 kVA

3.9 kVA

400 Vac

230 Vac

 

 

1.3 kVA 230 Vac

1.3 kVA

230 Vac

Figure 22 Example of Three-Phase Stacking Arrangement (Three Inverters)

When installing a three-phase system, the following rules must be observed.

Three-phase stacking requires a system display and a HUB.

The inverter that is mounted physically lowest is always the master and is programmed as Master. (See the system display manual for programming.) Mounting below the other inverters allows the master to avoid heat buildup and remain relatively cool, as it sees the greatest duty cycle.

The master must be connected to port 1 of the HUB. Other inverters must not be selected as master.

One slave inverter must be programmed as 3p Classic B. The other must be programmed as 3p Classic C. (See the system display manual for programming.)

The inverters should be wired to loads, and to AC sources, in phase order. The master should be phase A, the first slave should be phase B, and the second slave should be phase C.

All inverter wiring and input breakers must be sized for 30 Aac or less.

All inverters must be of the same model.

The AC input (generator or utility grid) must be 230/400 Vac at 50 Hz (a three-phase wye configuration).

When wiring the AC source to the inverters, local codes may require the inverter breakers to be located at the bottom of the main panel. This prevents overloading of the AC bus.

IMPORTANT:

Although the HUB manual states that it is necessary to move the HUB’s jumper to the three-phase position, that statement is not applicable for this model. The jumper must be left in its original position.

30

900-0111-01-00 Rev A

Image 32 Contents
International Series GFX Inverter/Charger Trademarks Symbols Used AudienceGeneral Safety DefinitionsPersonal Safety Inverter SafetyBattery Safety Regulatory Listings Recycling InformationEarth 911.com OurEarth.orgEuroRecycle.net Table of Contents List of Tables Welcome to OutBack Power Technologies ModelsComponents and Accessories IntroductionPlanning ApplicationsGenerator Battery BankRenewable Energy Planning Planning Dimensions Location and Environmental RequirementsTools Required MountingTerminals, Ports, and Features Terminals and PortsGrounding DC Ground LugDC Wiring DC Conductor Size and Torque Requirements InverterRequired Order of Battery Cable Hardware AC Wiring Multiple AC SourcesAccessory Wiring Accessory ConnectionsAUX Wiring AUX Connections for Vent Fan ExampleTwo-Wire Generator Start Example Automatic Generator Start AGSThree-Wire Generator Start Example Single-Inverter Installations Single-Inverter WiringMultiple-Inverter Installations Stacking Stacking ConnectionsParallel Stacking Dual-Stack and Larger Example of Parallel Stacking Arrangement Three InvertersParallel Wiring Four Inverters Three-Phase Stacking Example of Three-Phase Stacking Arrangement Three InvertersThree-Phase Wiring Three Inverters Functional Test Installation Installation Index Index Index Arlington, WA 98223 USA 34.93.654.9568 360.435.6030 Rev a
Related manuals
Manual 64 pages 8.19 Kb