NuTone CI-365 installation instructions Installation Option #2 in Walls Along Base Boards

Page 3

INSTALLATION

OPTION #2 - IN WALLS ALONG BASE BOARDS

Refer to Figure 3 (ACCESS TO PIPING FROM BELOW)

1.Locate studs (1) in the wall at the location VacPan™ will be installed.

2.VacPan™ should be located tight to one side in stud space.

3.Drill a small reference hole (2) through the floor under area of VacPan™. This will establish location from basement.

4.From below, use hole saw to remove wood floor and wood plate at location of VacPan™ between studs in wall cavity to provide access hole (3) from below.

5.Using a 11/2" hole saw, remove a 6 3/4" long slot (4) in baseboard tight to one stud.

1

1

2

4

3

FIGURE 3

Refer to Figure 4

6.Make wire connections to brass terminal and sprig terminal screws (5).

7.Secure VacPan™ (6) to baseboard using #6 screws provided.

8.From below, reach through hole (3) in stud space and push elbow (7) onto VacPan™ (6).

9.Make piping connections (8) as required to tie into existing central vac piping.

7

8

5

6

3

FIGURE 4

 

Image 3
Contents VacPan Automatic Dustpan Inlet Refer to Figure If Access Cannot be Made from belowInstallation Option #2 in Walls Along Base Boards Flooring contractor must run flooring under block Installation NEW Home Construction