Liebert SL-14050 installation and operation guide Drain Line, Steam Line

Page 8

5.ALWAYS supply and install a shut off valve in the water supply line dedicated to the humidifier to facilitate servicing. Use ½" OD copper to within 4 feet of the humidifier. Reduce copper to 3/8" OD and connect to the factory-supplied 3/8" olive compression fitting under the humidifier.

DRAIN LINE

1.Humidifier is equipped with a 7/8" O.D. unthreaded drain outlet on underside of drain canal on bottom of the humidifier (see Figure #15). A supplied reducer (see Figure #16)or equivalent shall be installed on the drain line. It will prevent backup in the drain pan and in the cylinder due to partially blocked or badly installed drain lines. This prevents rusting of the drain pan and arcing due to over-concentration. The drain canal has been improved to prevent backup despite long or gently sloped drain lines but it can not compensate for flat or uphill runs.

Figure #15

Drain Line Connection

B

Bottom View

A

 

 

 

 

 

 

Wall

MODEL

 

A in. (mm)

B

in. (Mm)

 

 

 

 

 

 

010-020

 

1.0 (25)

5.0 (127)

050-100

 

2.2 (55)

6.2 (158)

200

LEFT

2.2 (55)

6.2 (158)

200

RIGHT

2.2 (55)

19.6 (498)

Figure #16

codes prohibit it. Route to a floor drain or equivalent for safety reasons, since drain water from humidifier can be very hot.

3.Keep drain lines as short as possible. Keep drain lines sloped down, not level and not up since low spots in drain lines will accumulate sediment and cause backup. The drain line should be 1" O.D. copper pipe or larger. Do not use plastic pipe for drain lines.

STEAM LINE

1.Steam lines for SGH models 010 through 020 require a minimum 7/8" O.D. (nominal 3/4") copper pipe. For steam runs longer than 20 ft use insulated nominal 1" copper to ensure the draining of condensate.

2.Field-supplied hard copper with ½" thick snap-on insulation is recommended for steam supply, with Liebert supplied steam hose coupling used to make connection to cylinder. See Figure #17.

Figure #17

Steam Line Connection

 

 

Clamp To Steam Distributor

 

 

Or Remote Blower Pack

 

 

 

 

Field Supplied

 

 

 

 

 

 

 

 

 

 

 

 

Insulated Hard

 

 

 

 

Copper Pipe

 

 

 

 

Or Flexible

 

 

 

 

Steam Hose

See Section On

 

 

 

Available

 

 

 

 

Condensate

Trap

 

 

From Factory

 

 

 

 

 

Return Line

Figure #18

Sloping the Steam Line

Min. 10 Degree Slope

Factory Supplied Tapered cut is recommended

Air Gap

ClampAnd

7/8" I.D. Hose

Copper Reducer (1 1/4” - 3/4”) To Serve As Funnel Drain. Factory supplied.

3/4” Copper Pipe (Not Supplied)

Min. 12"

Trap

*See Section On Condensate

Return Line

NOTE: Steam hose should not reach bottom of the funnel. In the event the building drain is plugged this becomes an overflow point.

2.The drain line should not end in a sink used frequently by personnel, or where plumbing

NOTE: Trap must be 3' minimum down from steam distributor. If not, condensate must be routed to drain.

- 6 -

Image 8
Contents Installation Operation Guide Table Of Contents PRE-INSTALLATION Checkpoint Basic Humidifier ConfigurationReceiving & Unpacking Equipment Location & MountingBlower Packs See Figure #6 for mounting clearancesFront Side Steam DistributorsFigure #7 Steam Distributor Location Plumbing Water Supply LineDrain Line Steam LineFigure #19 Long Steam Lines Accessories Fill CUP Extension Kits Condensate Return LinePrimary Voltage Supply Wiring to Humidifier LOW Voltage Control WiringElectrical On-Off ControlsControls see Figure #28 Control InstallationOptional Modulation Continuous Manual Capacity Adjustment IntroductionSGH Operation Optional Modulation Continuous Control Packages by LiebertOther Potentiometers Detecting Water Supply DeficiencyRemote Indication Double Unit OperationLimited Warranty Cylinder Last Replaced