Calculate total input current requirements.

Input current requirements

Once you know the input power needed to operate the servers and other devices installed in the rack, you can calculate the input current that is required for the rack by using this formula:

Input Power (W)

Input/Current (A) = AC Voltage (V)

Using this basic formula, you can evaluate whether your PDU, UPS and/or local AC power circuit can provide the amount of current the equipment connected to it needs.

For example, if you are connecting four servers to a 16 A PDU, you can use the tables above and deter- mine the total input power requirements for each server. In this example let’s assume we have calculated these to be:

Server

Total Input Power (W)

 

 

HP Netserver LP 2000r #1

176

 

 

HP Netserver LP 2000r #2

177

 

 

HP Netserver LP 2000r #3

180

 

 

HP Netserver LP 2000r #4

180

 

 

The total input power requirements for these four servers come to 713 W. By knowing that we are operat- ing at a line power of 100 VAC and using the formula above we can calculate that the four servers will require an input current of 7.13 A—well below the capacity of the 16 A rated PDU.

Circuit breakers

The HP Netserver LP 2000r power supply has been designed for low AC inrush current to reduce the pos- sibility of tripping circuit breakers, typically located at a distribution panel.

Tripping of circuit breakers in the distribution panel may result from use of circuit breakers that are not adequately rated for inrush current found in most electronic devices. Replacing the circuit breaker with a suitable type is often the best solution.

The largest inrush current occurs when AC is first applied to the equipment in the rack. Often this inrush current is independent of the “on” or “off” state of the individual devices. However, you can usually reduce the total inrush current by applying power to the rack with the equipment in the “off” stage.

Power up sequence

Follow these instructions to minimize inrush currents and to minimize circuit breakers from tripping:

1.Power on peripherals one at a time; beginning with the tape back-up unit, followed by the mass-storage units, keyboard, video monitor, and mouse switch, if any.

2.If your system includes an HP Console Switch, it must be powered on before the HP Netserver LP 2000r.

3.Last, power on each HP Netserver LP 2000r and wait for the fan in each server to spin up before power- ing on the next one. If the HP Netserver LP 2000r doesn’t detect all the required components, it will not complete the boot process and will report an error.

Power down sequence

There is no specific order to power down the equipment in a rack; however, there is an HP recommenda- tion that it be done in the following sequence:

1.Ensure that the network users are properly warned of the power down.

2.Shut down the Network Operating System.

3.Power down the peripherals.

4.Power down the Netservers.

6

Image 11
Contents Planning your rack system for LP 2000r Hp netserver high Density rack solutions OverviewExecutive Summary HP Netserver website http//netserver.hp.com PublicationsWebsites Reader Assumptions Table of Contents HP Netserver High Density Rack Solutions Overview LP 2000r Safety Warnings Safety and Regulatory InformationGlossary HP Netserver High Density Rack Solutions Overview LP 2000r Planning your racked system Determine power requirements for the serversServer Power up sequencePower down sequence Circuit breakersX 3.41 = 2,431 BTU/Hr Input Power watts x 3.41=Thermal dissipation BTU/hrCheck your calculations Category Part Number Description Power consumption worksheet samplePower consumption worksheet actual Ventilation HP Rack System/EGauge columns provide strength Anti-tip foot Stability StrengthMobility Ease of UseFor Use with HP Rack Model Number HP Rack AccessoriesFor Use with HP Rack Model Number Content Front doors, side panels and tie kitsMount Fastener Cable Management AccessoryUse Tie Kit Kit Contains HP Rack System/E E7675A E77671A E7676A HP Power Distribution OptionsVoltage Current Outlets HP Product Number Type HP Netserver High Density Rack Solutions Overview LP 2000r Power = Vol ts x Amps Uninterruptible Power Supplies UPSAvailable Console SwitchDescription Includes HP Vertical Extension Kit Includes HP Rackmount Flat Panel Monitor and KeyboardHP Rack System/E Vertical Extension Kit Kit Contains HP Model NumberSlide mounting InstallationFlexible installation options Post HP System/E racks or EIA standard cabinetsMarking Rack Columns Marking the rackFixed, flush mounting Post EIA standard non-HP racks 3 optionsFixed, center mounting Location Marks on the Racks Front Columns Marking the RackPreparing the HP Netserver for 2-post rack installation Before you begin installationPDUs can be mounted on the rear Installing the Uninterruptible Power SuppliesInstalling the servers Installing Power Distribution UnitsAttach the main cable guides Cable ManagementHP System/E racks Attach the Cable Management ArmRoute the cables to their destination Begin routing the cablesSecure each cable bundle Maintain the ambient temperature Conclusion HP Netserver High Density Rack Solutions Overview LP 2000r