Sterling STT 160 manual STT 110 / STT Initial Operation, Switching on the Dryer

Page 17

SM2-605

STT 110 / STT 160

3.1. Initial Operation

Check whether the inlet of the drying hopper is closed by a blind lid, or whether a conveyor unit (optional) is installed.

If not, manufacture a suitable blind lid and install it on the inlet of the drying hopper or install the conveyor unit (optional).

F

Attachments which are not supplied by Sterling must be manufactured

according to the safety regulation European Standard 294.

Check whether the coolant circuit of the return air cooler is turned on (if a return air cooler is instal- led).

3.1.1. Switching on the Dryer

Switch on the main switch of the dryer.

&

The signal lamp “power” goes on.

 

 

For operation with timer clock (optional):

Turn the release switch “Timer” at position:

For operation without timer clock:

Turn the release switch “Timer” at position:

&

The blower is running.

 

 

F

If the dryer has not been in use for several months it must be operated for

about 2 hours without material.

Start up 3-2

Image 17
Contents Sterling Material Processing Operating Instructions Dehumidified air dryer STTParts and Service Department Edition 04/02 STT 110 / STT Sterling Material ProcessingSTT 110 / STT Table of contents Assembly instructions Transport, Assembly and StorageTechnical Data Spare parts list Electrical manualGeneral Information General InformationSTT 110 / STT STT 110 / STT Fields of applications CTT 110 / CTT Explanations and informationLegal basis Safety instructions Safety instructionsGeneral STT 110 / STT For your safetyOperation AssemblyMaintenance STT 110 / STT For the safety of the devices Start up Start upFor operation with timer clock optional Switching on the DryerFor operation without timer clock STT 110 / STT Initial OperationExit STT 110 / STT Continuous Operation Switching the Dryer onSTT 110 / STT Setting the Drying Temperature Optimizing the thermo regulator ExitSTT 110 / STT Switching the Dryer off Error and error correction Error and error correctionHopper heater Following errors can lead to an alarm BlowerRegeneration heater Maintenance MaintenanceSTT 110 / STT STT 110 / STT Maintenance schedule STT 110 / STT Cleaning or Replacing the Air Filter STT 110 / STT STT 110 / STT Cleaning or Replacing the Return Air FilterSTT 110 / STT Disposing of Drying Agents STT 110 / STT Cleaning the Drying Hopper STT 110 / STT ST 60 ST Functional description Functional descriptionSTT 110 / STT General Information STT 110 / STT STT 110 / STT STT 110 / STT Drying Hopper Optional STT 110 / STT Hopper Heater 180Return Air Cooler Optional Transport, Assembly and Storage Transport, Assembly and StorageSTT 110 / STT Tansport and Packing Storage STT 110 / STT AssemblyAssembly instructions Assembly instructionsGrounding the equipment against electrostatic charging STT 110 / STT Electrical Connection STT 110 / STT Connection of Return Air Cooler Optional Technical Data Technical DataSTT Return Air CoolerSTT 110 / STT STT 110 / STT Dimension Sheet Spare parts list Spare parts listDescription STT 110 / STT Pos ID-numberReturn air cooler optional Operating unit Pos ID-number Description Control unit Electrical manual Electrical manualAccessories AccessoriesParameter Parameter set Basic setting thermo regulatorCode