Maytag HRN4975S, HRP4975S, HRN5975S, HRP5975S manual Gas Piping

Page 17

1/2 pound per square inch (3.5kPa), the damage to the gas control valve could result in a fire or explosion from leaking gas.

FIGURE19.

All vent gases must be completely vented to the outdoors of the structure (dwelling). Install only the draft hood provided with the new water heater and no other draft hood.

Vent pipes must be secured at each joint with sheet metal screws.

There must be a minimum of 6 inches (153 mm) clearance between single wall vent pipe and any combustible material. Fill and seal any clearance between single wall vent pipe and combustible material with mortar mix, cement, or other noncombustible substance. For other than single wall, follow vent pipe manufacturer’s clearance specifications. To insure a tight fit of the vent pipe in a brick chimney, seal around the vent pipe with mortar mix cement.

Failure to have required clearances between vent piping and combustible material will result in a fire hazard.

Be sure vent pipe is properly connected to prevent escape of dangerous flue gases which could cause deadly asphyxiation.

Chemical vapor corrosion of the flue and vent system may occur if air for combustion contains certain chemical vapors. Spray can propellants, cleaning solvents, refrigerator and air conditioner refrigerants, swimming pool chemicals, calcium and sodium chloride, waxes, bleach and process chemicals are typical compounds which are potentially corrosive.

Gas Piping

Make sure the gas supplied is the same type listed on the model rating plate. The inlet gas pressure must not exceed 14 inch water column (2.6kPa) for natural and propane (L.P.) gas. If the gas control valve is subjected to pressures exceeding

If the main gas line Shut-off serving all gas appliances is used, also turn “OFF” the gas at each appliance. Leave all gas appliances shut “OFF” until the water heater installation is complete.

A gas line of sufficient size must be run to the water heater. Consult the current edition of the National Fuel Gas Code ANSI Z223.1/NFPA 54 and your gas supplier concerning pipe size.

There must be:

A readily accessible manual shut off valve in the gas supply line serving the water heater, and

A drip leg (sediment trap) ahead of the gas control valve to help prevent dirt and foreign materials from entering the gas control valve.

A flexible gas connector or a ground joint union between the shut off valve and control valve to permit servicing of the unit.

Be sure to check all the gas piping for leaks before lighting the water heater. Use a soapy water solution, not a match or open flame. Rinse off soapy solution and wipe dry.

The minimum inlet gas pressure shown on the rating plate is that which will permit firing at the rated input.

17

Image 17
Contents Series Nine Important Definitions Safe INSTALLATION, USE and ServiceSafety Precautions Table of Contents Customer Responsibilities Product SpecificationsAccessories Accessories and Tools NeededAdditional Tools Needed When Sweat Soldering ToolsRemoving the Old Water Heater Preparations for InstallationGET to Know Your Water Heater GAS Models Typical InstallationMixing Valve Usage Facts to Consider About the Location Locating and Installing the NEW Water HeaterInsulation Blankets ALL AIR from Inside Buildings See Figures 10 Water Piping Temperature-Pressure Relief Valve Filling the Water Heater Venting Gas Piping Sediment Traps GAS Piping with Flexible ConnectorOperating Instructions For Your Safety Read Before LightingFor Your Safety Read Before Lighting Temperature Time to Produce 2nd & 3rd Temperature RegulationTank Sediment Cleaning Service and MaintenanceBurner Cleaning Vent System InspectionHousekeeping Temperature-Pressure Relief Valve OperationAnode Rod Inspection DrainingDrain Valve Washer Replacement TroubleshootingService Start Up ConditionsSmoke / Odor Operational ConditionsLeakage Checkpoints Problem Cause Solution Troubleshooting GuideMaytag GAS Water Heaters Repair Parts ListPage Page Page Warranty