Heatiator GDST3831I owner manual Top Vent Horizontal Termination Three Elbows

Page 28

1. Top Vent - Horizontal Termination - (continued)

Three Elbows

Note: There MUST be a 25% reduction in total H when using flex vent except when using the simple up and out installation (see Figure 7.3).

V1 Minimum**

H1 + H2 Maximum

V2

V1 + V2 Min.

90 Elbow**

2 ft.

610 mm

*

*

 

 

 

 

 

 

1/2 ft.**

152 mm

6 ft.

1.8 m

*

*

 

 

 

 

 

 

1-1/2 ft.**

457 mm

10 ft.

3 m

*

*

2-1/2 ft.**

762 mm

12 ft.

3.7 m

*

*

3-1/2 ft.

1.1 m

14 ft.

4.3 m

*

*

 

 

 

 

 

 

H1 + H2 Max. =14 ft. (4.3 m)

*No specific restrictions on this value

EXCEPT V1 + V2 + H1 + H2 cannot exceed 40 ft. (12.2 m)

See Warning Below**

H2

V2

H1

WARNING**

Fire Risk.

When using SLP-HRC-SS and SLP-HRC-ZC-SS termination caps on top vented fireplaces, a one foot minimum vertical vent section is required before

installing first elbow.

When using DVP-TB1 termination cap on top vented fireplaces, a three foot minimum vertical vent section is required before installing first elbow.

When using any other cap, a section of vertical pipe (12 inches minimum) MUST be installed prior to attaching a 90° elbow.

Figure 7.6

V1

28

Heatilator • GDST3831I • 2127-900 Rev. K • 7/12

Image 28
Contents What to do if you smell gas ModelsHOT Surfaces Congratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingElectrical Information FinishingLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceLighting Instructions IPI Final inspection byWhat to do if YOU Smell GAS GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsBurner Ignition and Operation IPI Pilot Flame PatternsGetting Started Typical Appliance SystemTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase Minimum Framing DimensionsClearances Mantel and Wall Projections TOP View Fireplace OpeningTermination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Inches U.S.AInstall Support Brackets To Install the Heat ShieldContinue Adding Vent Components CorrectVent Information and Diagrams Approved PipeVent Table Key Use of ElbowsUse of Flex Vent Top Vent Horizontal Termination One Elbow Vent DiagramsV1 Minimum H1 Maximum Top Vent Horizontal Termination Two Elbows V1 Minimum H1 + H2 MaximumTop Vent Horizontal Termination Three Elbows V1 Minimum H1 + H2 Maximum V1 + V2 MinExhaust restrictor Instructions V1 Minimum Maximum V1 + V2 Min Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe SLPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Securing and Leveling the ApplianceInstalling Vent Pipe Assemble Vent SectionsAssemble Slip Sections Securing the Vent SectionsInstalling Decorative Ceiling Components Disassemble Vent SectionsInstalling Metal Roof Flashing Assemble and Install Storm CollarInstalling Decorative Wall Components Installing Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap 17 Venting through the wallGas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Optional Accessories RequirementsElectrical Information Code CSA C22.1Intellifire Ignition Wiring Diagram with Remote Receiver Junction Box Installation Wall Switch Installation for Fan OptionalSides using a 300 F minimum sealant. Refer to FinishingFacing Material Metal front faces may be covered with non-combustibleTo install the Splatter Guard Splatter GuardTo Close the Lower Access Panel To Remove the Splatter GuardAppliance Setup Install the Log Assembly Models ST-550T-IPI. GDST3831INotch Air Shutter Setting Install Trim Kits and SurroundsAir Shutter Settings Symptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Specifications. Polish flame sensing rod with fine steel wool Electrical Access Left View Front View GAS Line Right View Appliance Dimension DiagramReference Materials  B. Vent Components Diagrams Vent Components Diagrams SLP-TVHW330 mm 34 mm14-1/16 357 mmSLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP DVP-TB1 Horizontal Termination CAPOptional Wire Harness SLP-LPCService Parts Log Set AssemblyStocked At Depot#9 Valve Assembly StockedService Parts List Contact Information Do not Discard this Manual