4.For thin walls (1/2" or less), insert red key into wall anchor. Push red key to “pop” open anchor wings. IMPORTANT: Do not hammer key!

For thick walls (over 1/2" thick) or solid walls, do not pop open wings.

Figure 7 - Popping Open Anchor Wings For Thin Walls

5.Place mounting bracket onto wall. Line up last hole on each end of bracket with wall anchors.

6.Insert mounting screws through bracket and into wall anchors.

7.Tighten screws until mounting bracket is firmly fastened to wall.

Placing Heater On Mounting Bracket

1.Locate two horizontal slots on back panel of heater.

2.Place heater onto mounting bracket. Slide horizontal slots onto stand-out tabs on mounting bracket.

Horizontal Slots

Stand-Out Tab

Mounting Bracket (attached to wall)

Figure 8 - Mounting Heater Onto Mounting Bracket

Installing Bottom Mounting Screws

1.Locate two bottom mounting holes. These holes are near bottom on back panel of heater (see Figure 9).

2.Mark screw locations on wall.

3.Remove heater from mounting bracket.

4.If installing bottom mounting screws into hollow or solid wall, install wall anchors. Follow steps 1 thru 4 under Attaching To Wall Anchor Method, page 8. If installing bottom mounting screw into wall stud, drill holes at marked loca- tions using 9/64" drill bit.

5.Replace heater onto mounting bracket.

6.Place spacers between bottom mounting holes and wall anchor or drilled hole.

7.Hold spacer in place with one hand. With other hand, insert mounting screw through bottom mounting hole and spacer. Place tip of screw in opening of wall anchor or drilled hole.

8.Tighten both screws until heater is firmly secured to wall. Do not over tighten. Note: Do not replace front panel at this time. Replace front panel after making gas connections and checking for leaks (see pages 10-12).

Figure 9 - Installing Bottom Mounting Screws

9

Image 9
Contents What to do if YOU Smell GAS OWNER’S Operation and Installation ManualContents Safety Information Safety Information Local Codes Unpacking Product Features Safety DevicePiezo Ignition System Installation Items Check GAS TypeLocating Heater Combustible Material SurfaceMounting Bracket Installing Heater to WallRemoving Front Panel Of Heater Methods For Attaching Mounting Bracket To WallAttaching Mounting Bracket To Wall Marking Screw LocationsPlacing Heater On Mounting Bracket Installing Bottom Mounting ScrewsConnecting to GAS Supply Checking GAS Connections Pressure Testing GAS Supply Piping SystemManual Shutoff Valve Pressure Testing Heater GAS ConnectionsFor Your Safety Read Before Lighting Operating HeaterLighting Instructions Turn counterclockwise Inspecting Burner Manual Lighting ProcedureTo Turn OFF GAS to Appliance Pilot Flame PatternCorrect Burner Flame Pattern Burner Flame PatternODS/PILOT and Burner Cleaning and Maintenance Trouble ShootingCabinet Air PassagewaysCleaning From Top Ing statement atService Hints Technical ServiceReplacement Parts Parts Under WarrantyParts Not Under Warranty Valve GA5010 AccessoriesODS/Pilot KEY Part Number Description QTY Parts ListPage Page International Warranty Information