Trane SCRH, SCWH Isolator Placement, pre-installation Installation considerations, 1 7/8, 3 3/4

Page 9
Isolator Placement

Isolator Placement

Note: Isolators are field-provided.

pre-installation

Installation considerations

Table I-PC-1. Isolator load points, units with a vertical discharge configuration, lbs.

model

L1

L2

L3

L4

L1

L2

L3

L4

 

 

SCRB/SIRB

 

 

SCWB/SIWB

 

 

 

 

 

 

 

 

 

 

 

 

3-ton

99

105

120

127

105

133

118

124

 

5-ton

115

122

157

166

129

165

166

165

 

7.5-ton

154

203

227

221

177

234

230

231

 

10-ton

208

266

273

253

263

334

293

300

 

15-ton

243

332

359

356

315

388

382

375

 

Table I-PC-2. Isolator load points, units with a horizontal discharge configuration, lbs.

model

L1

L2

L3

L4

L1

L2

L3

L4

 

 

SCRB/SIRB

 

 

SCWB/SIWB

 

 

 

 

 

 

 

 

 

 

 

 

7.5-ton

250

108

313

135

285

126

319

140

 

10-ton

318

150

363

169

383

211

383

211

 

15-ton

404

166

510

210

514

215

514

215

 

Table I-PC-3. Isolator load points & types, units with a horizontal discharge, inverted “L” configuration, lbs.

 

 

air-cooled models

 

water-cooled models

 

L1

L2

L3

L4

L1

L2

L3

L4

10-ton unit

 

 

 

 

 

 

 

 

318

150

363

169

383

211

383

211

spring

red

yellow

red

yellow

red

yellow

red

yellow

rubber-in-shear

green

red

green

red

green

red

green

red

 

 

 

 

 

 

 

 

 

15-ton unit

404

166

510

210

514

215

514

215

spring

purple

yellow

purple

yellow

purple

yellow

purple

yellow

 

 

 

 

 

 

 

 

 

rubber-in-shear

gray

red

gray

red

gray

red

gray

red

Note: Units ship with two different color isolators and should be placed as depicted in this chart to properly support the unit weight. See Figures I-PC-1 & I-PC-2 for correct isolator positions by unit size.

3, 5, & 7.5-ton units

bottom view of unit

L1

L3

Note: Isolators are field-provided. L2L4 1 7/8

7/8” dia. hole under all 4 corners

10 & 15-ton units

bottom view of unit

L1

L3

L2

L4

1 7/8

 

9/16” dia. hole under all 4 corners

 

1 3/8

1 7/8

3 3/4

Figure I-PC-1. Isolator mounting hole locations on 3, 5, &

Figure I-PC-2. Isolator mounting hole locations on 10 & 15-

7.5-ton units

ton units

PKG-SVX14A-EN

9

Image 9
Contents October “AO” and later design sequenceInstallation, Operation, and Maintenance Midrange Self-ContainedUnitsWarnings and Cautions general informationExample Warnings and Cautions Special Note on Refrigeration EmissionsInstallation…………………………………………………2 contentsMaintenance ……………………………………………25 Operation…………………………………………………24Unit Airflow Configurations Installation informationgeneral Midrange Model Number Descriptiongeneral Refrigerant Handling ProceduresGeneral Installation informationInstallation Preparation pre-installation Installation considerationsReceiving and Handling Pre-InstallationConsiderationsService Access pre-installation Installation considerations3 through 7.5-tonSCRH/SCWH pre-installation Installation considerations Service Access10 through 15-tonSCRH/SCWH pre-installation Installation considerations Isolator PlacementNote Isolators are field-provided 1 7/8Proper Lifting Procedure pre-installation Installation considerationsImproper Unit Lift Installation weights dimensions &3 & 5-tons SCWH/SCRH vertical discharge SCWHdimensions 7.5-tons SCWH/SCRHInstallation weights vertical dischargedimensions SCWH/SCRHInstallation weights SCWH/SCRH dimensions & weight, in-lbsInstallation weights dimensionsSCWH/SCRH Dimensions, in SCWH/SCRHdimensions PlenumInstallation weights Hot water coil 3 & 5-tonunits7.5-tonunits Hot water coilHot water coil 10 thru 15-tonunits dimensionsDuct Connections Installation requirementsmechanical Water PipingElectrical Requirements Refrigerant Piping Air-CooledUnits OnlyInstallation requirements Brazing ProceduresElectrical Data Calculations electricalInstallation requirements Supply Power Wiringelectrical Installation requirementsHazardous Voltage Table I-ER-1.Model SCWH/SCRHelectrical dataInstallation procedure installationInstallation Checklist Plenum Installationpre-startup Pre-StartupChecklistInstallation requirements ReceivingUnit Startup Procedures Installation startupUnit Startup Checklist Hazardous voltagesequence of Operation operationSequence of Operation Maintenance information Table M-GI-1.Midrange maintenance general datageneral Maintenance procedures maintenanceMaintenance Procedures Periodic Maintenance Checklistmaintenance Refrigerant SystemMaintenance procedures Leak TestingMaintenance procedures maintenanceMotor Winding Damage Hazardous PressuresPeriodic Checklists Maintenance checklistsperiodic Monthly ChecklistMaintenance troubleshooting TroubleshootingHazardous voltage Maintenance troubleshooting Insufficient coolingHazardous voltage Maintenance diagram typical wiringtypical wiring Maintenance diagramPKG-SVX01A-EN Maintenance diagram typical wiringtypical wiring Maintenance diagramPKG-SVX01A-EN PKG-SVX14A-EN Literature Order NumberDate October