G. Cut out Hole in Roof

G. Cut out Hole in Roof

Refer to Figure 8.9.

Plumb from roof to center of chimney.

Drive a nail up through roof to mark center of pipe.

Measure to either side of nail and mark the 14-1/2 in. x 14-1/2 in. (368 mm x 368 mm) opening required.

Measure opening on the horizontal; actual length may be larger depending on roof pitch.

Cut out and frame opening.

Refer to Chapter 25 of the Uniform Building Code for roof framing details.

H. Complete Installation

WARNING! Risk of Fire! You MUST maintain 2 in.

(51 mm) air space to insulation and other combustible materials around the chimney system. Failure to do so could cause overheating and fire.

Keep chimney sections from separating or twisting.

You may secure straight chimney sections at the joints with screws no longer than 1/2 in. (13 mm).

The following steps should be skipped if using a chase.

Install roof flashing appropriate to roof pitch.

Install round termination cap and storm collar following instructions shipped with the cap.

I. Install Flashing

Assemble chimney so it passes through the framed opening.

Slip the flashing over the chimney.

NOTICE: Roofing shingles must be below the flashing plate on the lower side of a sloped roof and over the flashing plate on the sides and top.

Nail the flashing to the roof. Keep gaps between the flashing plate and the roof to a minimum.

Caulk the flashing plate and roof junction as well as the vertical seam on the flashing. All nail heads must be caulked with a roofing sealant.

Figure 8.9 Ceiling/Attic Construction

Heat & Glo • EM-415, EM-485 • 33056 • Rev V • 05/08

29

Image 29
Contents Circulating Wood Burning FireplaceModels EM-415, EM-415H,36” EM-485T, EM-485TH,42” Homeowner Reference Information CongratulationsListing Label Information/Location FIREPLACE NOInstaller Guide Table of ContentsSafety Alert Key User GuideWARRANTY FOR HEAT & GLO FIREPLACES A. Appliance Certification 1 Listing and Code ApprovalsB. Non-CombustibleMaterials C. Combustible Materials2 Operating Instructions User GuideA. Your Fireplace Hot glass will cause burnsC. Starting a Fire B. Seasoned WoodD. Grate E. FirescreenK. Vented Gas Log Sets & Gas Log Lighters H. Glass DoorsL. Optional Components M. Clear SpaceHardwood vs Softwood N. Wood FuelMoisture Seasoned WoodB. Chimney Inspection/Cleaning 3 Maintainance and ServiceA. Disposal of Ashes Creosote - Formation and Need for RemovalC. Check Firebox Refractory E. Glass CleaningD. Inspect Grate Frequency As desiredStart Fire Problems 4 Troubleshooting GuideSolution Possible Cause5 Getting Started Installer GuideA. Typical Fireplace System Illustrations/diagrams are not drawn to scaleD. Negative Pressure B. Design and Installation ConsiderationsC. Draft E. Locating Fireplace & Chimney H. Inspect Fireplace and Components F. Tools and Supplies NeededG. Typical Fireplace System A. Select Fireplace Location 6 Framing & ClearancesB. Clearances D. Frame the Fireplace C. Sidewalls/Surrounds2 in. 51 mm min. air space clearance from chimney C A BA. Things to Consider 7 Installation of FireplaceB. Position the Fireplace C. Place Protective Metal Hearth Stripsin Canada Note Chimney air kitnot shown, but required F. Junction Box Installation E. Install Outside Air KitBend this half tab 90 degrees down 90 degrees G. Installation of FanBend this tab down 8 Chimney Assembly A. Chimney Requirements B. Using Offsets/Returns C. Assembling Chimney Sections D. Install Chimney Air KitE. Installing Ceiling Firestops F. Installing Attic Insulation Shield I. Install Flashing H. Complete InstallationG. Cut out Hole in Roof WARNING! Risk of Fire! You MUST maintain 2 inJ. Chimney Termination Requirements A. Construct the Chase 9 Chase InstallationsC. Install Chase Top B. Install Fireplace & ChimneyRefer to termination cap instructions D. Install Termination CapTR344 Round Termination Cap TR342 Round Telescoping Termination CapTCT375 Terra Cotta Cap TS345/TS345P Square Termination CapEuropean Copper Series Termination Cap B. Field Constructed Shrouds 10 ShroudsA. Radiation Shield Roofed Style Shroud radiation shield required Mailbox Style Shroud radiation shield requiredA. Non-CombustibleMaterials 11 FinishingB. Combustible Materials C. Hearth ExtensionWARNING! Risk of Fire D. Finishing MaterialF. Sidewalls/Surrounds E. Combustible Mantel10 3/4 in 273 mm 4in 102 mm 9 3/4 in 248 mmC. Install Fan 12 AccessoriesA. Gas Log/Lighter Provision B. Wood Burning InsertsPage Catalog # B. Fireplace ComponentsDescription Catalog #1/2 in 13 mm B. Fireplace Components continued66 in 1676 mm 20 in 508 mm Catalog # C. Chimney Components368 mm 14-1/2inCatalog # 10-7/8in 276 mm 2 in. 51 mmCatalog # European Copper Caps EM-415SERIES Service PartsD. Service Parts Service Parts ListService Parts EM-485SERIESService Parts List Beginning Manufacturing Date N/AThis page intentionally left blank This page intentionally left blank DO DISCARDNOT E. Contact InformationDO NOT DISCARD THIS MANUAL