1 + 2 + 3 + 4 = 270°

1

2

3

4

FP1179

Fig. 24 Maximum elbow usage.

4.Proceed to plumb for additional openings through the roof. In all cases, the opening must provide a mini- mum of 1” (25 mm) clearance to the vent pipe, i.e., the hole must be at least 9³⁄” x 9³⁄” (240 x 240 mm).

5.Place fireplace into position.

6.Place firestop(s) #7DVFS or Attic Insulation Shield #7DVAIS into position and secure. (Fig. 26)

7.Install roof support (Fig. 25) and roof flashing making sure upper flange is below the shingles. (Fig. 28)

8.Install appropriate pipe sections until the venting is above the flashing. (Fig. 28)

9.Install storm collar and seal around the pipe.

10.Add additional vent lengths for proper height. (Fig. 28)

11.Apply high temperature sealant to 4” and 7” collars of vertical vent termination and install.

If there is a room above ceiling level, fire stop spacer must be installed on both the bottom ad the top side of the ceiling joists. If an attic is above ceiling level a 7DVAIS (Attic Insulation Shield) must be installed.

The enlarged ends of the vent section always face downward.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Typical Roof

 

 

 

 

 

 

 

 

 

 

Support

Typical Ceiling

Application

 

Support

 

 

 

Application

 

 

 

 

 

 

 

FP1184

 

 

 

 

 

 

 

 

Fig. 25 Venting supports.

 

 

 

 

 

Brookhaven Direct Vent Gas Fireplace

Attic Insulation Shield

Upper Floor

11”

11”

(279mm)

(279mm)

 

Ceiling Installation

Joist

 

 

Firestop

 

Spacer

Nails (4)

FP1029

 

Fig. 26 Place firestop spacer(s) and secure.

Min.

2' (610 mm)

FP1185

Fig. 27 Minimum termination to roof clearance.

3 #5 Sheet Metal

Screws per Joint

Sealant

Storm Collar

TWL101a

Fig. 28 Roof flashing.

10009459

15

Image 15
Contents Brookhaven Direct Vent Model 20DVT Table of Contents Installation & Operating Instructions Locating Your FireplacePlease Review the Following Carefully 20DVT Fireplace Dimensions Framing Dimensions20DVT Clearance to Combustibles MantelsHearth Gas Specifications Gas Line InstallationFraming and Finishing Final FinishingRemote ON/OFF Switch General VentingLocation of Vent Termination General Venting Information Termination Location Canadian Installations1 US Installations2Flex Vent Pipes Canadian InstallationsUSA Installations General Information Assembling Vent PipesExample a How to Use the Vent GraphTwist Lock Pipes Vertical Sidewall ApplicationsVertical Sidewall Installation Twist Lock Pipe Total angular variation =Step Zero clearance sleeve is only required for combustible walls Always install horizontal venting on a level planeBelow Grade Installations Vertical Sidewall Installation Flex Vent PipeVertical Through-the-Roof Application Vertical Through-the-Roof InstallationVenting supports Venting Components Glass Information Glass CleaningWindow Frame Assembly Removal Operating InstructionsLogs 20DVT Installation of LogsLog Identification Chart Log InstallationInspecting the Venting System Flame & Temperature AdjustmentFlame Characteristics Large Lava RockWhat to do if YOU Smell GAS To Turn Off Gas To HeaterSIT Nova 820 Millivolt Valve Troubleshooting the Gas Control SystemProceeding Nova SIT820 Valve ConversionBurner Orifice Conversion Pilot Orifice Conversion Maintenance Cleaning the Standing Pilot Control SystemBurner and Burner Compartment 8a,b 7a,b DescriptionFuel Conversion Kits 20DVTOptional Trim Kits Optional Accessories AvailableRemote Controls Ceramic Refractory PanelsBrookhaven Direct Vent Gas Fireplace Brookhaven Direct Vent Gas Fireplace Brookhaven Direct Vent Gas Fireplace If Warranty Service is NEEDED… Product Covered by this WarrantyAFUE% Efficiency Ratings