Lochinvar 400, 801 operation manual Gas Pressure, Gas valve replacement

Page 49

7 Gas connections (continued)

Installation & Operation Manual

￿WARNING

When re-tightening the set screw, be sure to tighten securely to prevent gas leaks.

Do not check for gas leaks with an open flame -- use the bubble test. Failure to use the bubble test or check for gas leaks can cause severe personal injury, death, or substantial property damage.

Figure 7-7Inlet Gas Supply Check - Models 601 - 801

REMOVE THE 1/8” (3 MM) PIPE PLUG ON THE INLET FLANGE TO THE VALVE AND INSTALL A SUITABLE 1/8” (3 MM) FITTING (FIELD SUPPLIED) FOR THE MANOMETER TUBING.

14.Turn on the gas supply at the manual gas valve.

15.Turn the power switch to the “ON” position.

16.Adjust the temperature set point on the control panel of the SMART SYSTEM control module to the desired water temperature so the appliance will call for heat.

17.Check burner performance by cycling the system while you observe burner response. The burner should ignite promptly. Flame pattern should be stable. Turn system off and allow burner to cool, then cycle burner again to ensure proper ignition and flame characteristics.

Figure 7-5Inlet Gas Supply Check - Model 400

LOOSEN THE SET SCREW ONE (1) FULL TURN

AND PLACE THE MANOMETER TUBING OVER

THE PRESSURE TAP.

Figure 7-6Inlet Gas Supply Check - Model 501

DETAIL

Gas Pressure

The gas pressure must remain between 4 inches w.c. (.99 kPa) minimum and 14 inches w.c. (3.5 kPa) maximum for Natural gas and between 8 inches w.c. (1.9 kPa) minimum and 14 inches w.c. (3.2 kPa) maximum for LP gas during standby (static) mode and while in operating (dynamic) mode. If an in-line regulator is used, it must be a minimum of 10 feet (3 m) from the Knight XL boiler. It is very important that the gas line is properly purged by the gas supplier or utility company. Failure to properly purge the lines or improper line sizing, will result in ignition failure.

The problem is especially noticeable in NEW LP installations and also in empty tank situations. This can also occur when a utility company shuts off service to an area to provide maintenance to their lines.

Gas valve replacement

LOOSEN THE SET SCREW ONE (1) FULL TURN AND PLACE THE MANOMETER TUBING OVER THE PRESSURE TAP.

The gas valve MUST NOT be replaced with a conventional gas valve under any circumstances. As an additional safety feature, this gas valve has a flanged connection to the venturi and blower.

DETAIL

￿WARNING

￿WARNING

Failure to follow all precautions could result in fire, explosion, or death!

DO NOT adjust or attempt to measure gas valve outlet pressure. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.

49

Image 49
Contents Models 400 Contents Please read before proceeding When servicing boilerStainless steel heat exchanger Knight XL How it worksModel Models 601 Knight XL Boiler =B=R Rating RatingsCloset and alcove installations Installation must comply withDetermine boiler location Before locating the boiler, checkAlcove Installation Provide air openings to room Residential garage installationVent and air piping Flooring and foundationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet Prepare boilerGas conversions Model Leveling the boiler Models 601General venting Direct venting options Vertical Vent Requirements for installation in Canada Install vent and combustion air pipingInstalling vent or air piping General ventingVent Pipe, and Fittings PVC/CPVC air intake/vent connectionsStainless steel vent Air inlet pipe materialsStainless Steel Air Intake/vent Connections FasNSeal Saf-T VentRemoving from existing vent Optional room airAir contamination Model Description Kit NumberSidewall direct venting If using the alternate sidewall terminationVent/air termination sidewall Determine location3AClearance to Gravity Air Inlets Bird Screen Typical Prepare wall penetrationsMultiple vent/air terminations Prepare wall penetrations Alternate Field Supplied OptionTermination and fittings Description and usage Sidewall termination installation9Concentric Vent Dimensional Drawing Models 400 Multiventing sidewall terminations 11Concentric Vent Sidewall AttachmentVent/air termination vertical Vertical direct ventingMultiple vent/air terminations Prepare roof penetrations4Concentric Vertical Termination Vertical termination installationMm see -9, Multiventing vertical terminationsConcentric Venting Arrangement Alternate vertical concentric venting10Existing Vent as a Chase Existing vent as a chaseSystem water piping methods General piping information Hydronic pipingLow water cutoff device Chilled water systemHydronic piping Near boiler piping components Flow switch adjustmentCirculator sizing Near boiler piping connectionsVariable speed pump option Pressure Head Feet20F 25F 30F 35F Model 7Single Boiler Multiple Temperatures 8Single Boiler Primary/Secondary Piping Manifold Pipe Sizes in Inches mm Number of Units10Multiple Boilers Primary/Secondary Piping Loop Gas connections Connecting gas supply pipingPropane Gas Natural gasInches Check inlet gas supplyGas Pressure Gas valve replacementInstallation must comply with Field wiringLine voltage connections Low voltage connectionsLouver proving switch Outdoor temperature sensorHigh gas pressure switch Low gas pressure switchAlarm contacts Flow switchWiring of the cascade ModbusManual Condensate drain Condensate disposalStart-up Freeze protection when usedCheck/control water chemistry Fill and test water systemCheck thermostat circuits Check for gas leaksInspect/fill condensate system Inspect/check condensate lines and fittingsStart the boiler Final checks before starting the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Natural Gas Propane Set space heating operationSet domestic hot water DHW operation Verify DHW modeConfiguration of the cascade General Operating informationProtection features Boiler temperature regulation Cascade Outdoor reset operation, if usedOperation Display Sequence of operationStandby, ready to start a new cycle Navigation Dial Knight XL control moduleInstaller Access modesUser Call for Heat Information Dial Function Service technician Maintenance Maintenance and annual startupInstructions Address reported problems MaintenanceClean condensate trap Check all piping for leaks Inspect boiler areaCheck water system Flue vent system and air pipingCheck expansion tank Check boiler relief valveCheck all boiler wiring Check ignition ground wiringCheck control settings Inspect ignition and flame sense electrodesCleaning boiler heat exchanger Check flame signalReview with owner Model Kit Part Component Number DescriptionLOW Voltage 120 VAC High Voltage Diagrams2Ladder Diagram Page KBXII-I-O Rev D
Related manuals
Manual 16 pages 54.19 Kb Manual 48 pages 13 Kb

400, 801 specifications

The Lochinvar 801,400 is a cutting-edge solution in the realm of high-efficiency commercial water heating. This model represents a significant advancement in the design and functionality of water heaters, catering primarily to the demands of large-scale facilities like hotels, hospitals, and large industrial operations.

One of the standout features of the Lochinvar 801,400 is its impressive heating capacity, which can produce up to 801,400 BTUs, making it suitable for high-demand applications. This output is crucial for establishments that require a consistent supply of hot water, such as commercial kitchens and laundry facilities. The robust design ensures that it can handle peak demand periods without compromising performance.

Another significant aspect is the innovative use of advanced technology in its operation. The Lochinvar 801,400 integrates smart controls that enhance its efficiency and ease of operation. These controls allow for precise monitoring and adjustment of water temperatures, ensuring that the system operates within optimal parameters while maximizing energy savings. The intelligent monitoring system can provide real-time updates, making it easier for facility managers to keep track of performance and address maintenance needs proactively.

The construction of the Lochinvar 801,400 incorporates durable materials that not only enhance the longevity of the unit but also offer resistance to corrosion and wear. This durability translates into lower maintenance costs and an extended lifespan for the unit, making it a worthwhile investment for businesses.

Moreover, the Lochinvar 801,400 is designed with energy efficiency in mind. It boasts a high thermal efficiency rating, which reduces operational costs and minimizes the carbon footprint of heating operations. This efficiency is critical in today’s environmentally conscious market, where businesses are seeking to reduce their energy consumption and comply with strict regulations.

The design of the Lochinvar 801,400 also prioritizes safety, featuring innovative safety controls and fail-safes that protect both the unit and the users.

In summary, the Lochinvar 801,400 offers a combination of high capacity, advanced technology, durability, and energy efficiency, making it an excellent choice for commercial water heating solutions. As industries continue to evolve, the demand for reliable and efficient water heating solutions like the Lochinvar 801,400 will only increase.