Hearth and Home Technologies SC60 owner manual TS345/TS345P Square Termination Cap

Page 34

TS345/TS345P Square Termination Cap

Termination Cap

Collar

2 in. (51 mm)

Minimum Height

Chase Top

Chimney

Pipe

Place waterproof sealer under each flange of the termina- tion cap and on top of each screw to help prevent leaks.

3 in. (76 mm)

Maximum

top of chase to top of

chimney section

Chase

Termination cap pipe and chimney section must overlap 1-1/2 in. (38 mm).

Figure 9.7 Installing a TS345/TS345P Square Termination Cap

TCT375 Terra Cotta Cap

Collar

2 in. (51 mm)

Minimum Height

Chase Top

Place waterproof sealer under each flange of the termina- tion cap and on top of each screw to help prevent leaks.

Termination Cap

The last section of pipe must stop between 2 in. (51 mm) above top of chase and 7 in. (178 mm) below top of chase

2 in. (51 mm)

7 in. (178 mm)

Chase

Chimney

Pipe

Termination cap pipe and chimney section must overlap 1-1/2 in. (38 mm)

Figure 9.8 Installing a TCT375 Terra Cotta Cap

34

Heatilator • SC60 • 32838 Rev X • 10/08

Image 34
Contents Hot screen/mesh and glass doors will cause burns Wood Burning FireplaceFire Risk Grate Listing Label Information/LocationNumber Safety Alert Key Table of ContentsInstaller Guide User GuideHearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityHeatilator SC60 32838 Rev X 10/08 Non-Combustible Materials Listing and Code ApprovalsAppliance Certification Combustible MaterialsYour Fireplace Operating InstructionsHot glass will cause burns Grate Seasoned WoodStarting a Fire FirescreenOptional Components Glass DoorsVented Gas Log Sets & Gas Log Lighters Clear SpaceWood Fuel Disposal of Ashes Maintainance and ServiceChimney Inspection/Cleaning Creosote Formation and Need for RemovalInspect Grate Glass CleaningCheck Firebrick Frequency As desiredTroubleshooting Guide Start Fire Problems Possible Cause SolutionGetting Started Typical Fireplace SystemDraft Design and Installation ConsiderationsNegative Pressure Locating Fireplace & Chimney Frequently open doors Central heat outlets or returnsFireplace System Requirements Tools and Supplies NeededInspect Fireplace and Components Framing & Clearances Select Fireplace LocationClearances Clearances to Combustible MaterialsSidewalls/Surrounds Frame the FireplacePosition the Fireplace Installation of FireplaceThings to Consider Place Protective Metal Hearth StripsFt min. from top of uppermost chimney section to air inlet Install Outside Air Kit To service or replace the fan kitChimney Assembly Chimney Requirements Height of Chimney ComponentsUsing Offsets/Returns ExampleInstall Ceiling Firestops Install Chimney Air KitAssemble Chimney Sections Install Attic Insulation Shield Prepare Attic Insulation ShieldFollowing steps should be skipped if using a chase Complete InstallationInstall Flashing Cut out Hole in RoofChimney Termination Requirements Flat Roofs Chase Installations Construct the ChaseInstall Fireplace & Chimney Install Chase TopInstall Termination Cap ST375 Square Termination CapTS345/TS345P Square Termination Cap Field Constructed Shrouds ShroudsRadiation Shield Open Top Shroud TR342 caps require radiation shieldMailbox Style Shroud radiation shield required Roofed Style Shroud radiation shield requiredHearth Extension Finishing= 1/k x inches of thickness Finishing Material HX3 or HX4 Hearth Ext or equivilent insulationCombustible Mantel Firebrick Installation 13 Side Brick InstallationWood Burning Inserts AccessoriesGas Log/Lighter Provision Gas Code, Ansi Z223.1Materials Fireplace1321 mm 406 mm Chimney Components Catalog #14-1/2 10-7/8 276 mm Service PartsContact Information
Related manuals
Manual 48 pages 44.95 Kb