CAUTION: Use only new, black iron or steel pipe. Inter- nally-tinned copper tubing may be used in certain areas. Check your local codes. Use pipe of 1/2" diameter or greater to allow proper gas volume to heater. If pipe is too small, undue loss of pressure will occur.

Installation must include a manual shutoff valve, union, and plugged 1/8" NPT tap. Locate NPT tap within reach for test gauge hook up. NPT tap must be upstream from heater (see Figure 13).

Apply pipe joint sealant lightly to male threads. This will prevent excess sealant from going into pipe. Excess sealant in pipe could result in clogged heater valves.

CAUTION: Use pipe joint seal- ant that is resistant to liquid pe- troleum (LP) gas.

Install sediment trap in supply line as shown in Figure 13. Locate sediment trap where it is within reach for cleaning. Locate sedi- ment trap where trapped matter is not likely to freeze. A sediment trap traps moisture and contaminants. This keeps them from going into heater controls. If sediment trap is not installed or is installed wrong, heater may not run properly.

CAUTION: Avoid damage to regulator. Hold gas regulator with wrench when connecting it to gas piping and/or fittings.

CHECKING GAS

CONNECTIONS

WARNING: Test all gas pip- ing and connections for leaks after installing or servicing. Cor- rect all leaks at once.

WARNING: Never use an open flame to check for a leak. Apply a mixture of liquid soap and water to all joints. Bubbles forming show a leak. Correct all leaks at once.

CAUTION: Make sure exter- nal regulator has been installed between propane supply and heater. See guidelines under Con- necting to Gas Supply, page 10.

Pressure Testing gas Supply Piping system

Test Pressures In Excess Of 1/2 PSIG

1.Disconnect heater and its individual manual shutoff valve from gas supply piping system. Pressures in excess of 1/2 psig will damage heater regulator.

2.Cap off open end of gas pipe where manual shutoff valve was connected.

3.Pressurize supply piping system by ei- ther using compressed air or opening propane supply tank valve.

4.Check all joints of gas supply piping system. Apply mixture of liquid soap and water to gas joints. Bubbles form- ing show a leak.

5.Correct all leaks at once.

6.Re-connect heater and manual shutoff valve to gas supply. Check re-con- nected fittings for leaks.

Test Pressures Equal To or Less Than 1/2 PSIG

A.G.A. Design-Certified Manual

Shutoff Valve With 1/8" NPT Tap*

From Propane

Approved Flexible Gas Hose

Tank (11" W.C.**

(if allowed by local codes)

to 14" W.C.

 

Gas

Pressure)

 

Control

 

 

Tee Joint

3" Minimum

Pipe

 

Nipple

 

Cap

 

Sediment Trap

Figure 13 - Gas Connection

*Purchase the optional A.G.A. design-certified manual shutoff valve from your dealer. See Accessories, page 21.

**Minimum inlet pressure for purpose of input adjustment.

1.Close manual shutoff valve (see Fig- ure 14, page 12).

2.Pressurize supply piping system by ei- ther using compressed air or opening propane supply tank valve.

3.Check all joints from propane supply tank to manual shutoff valve (see Fig- ure 15, page 12). Apply mixture of liq- uid soap and water to gas joints. Bubbles forming show a leak.

4.Correct all leaks at once.

Continued

104307

11

Image 11
Contents What to do if YOU Smell GAS Safety Information Unpacking Product FeaturesProduct Identification Local CodesConfined Space and Unconfined Space AIR for Combustion and VentilationProviding Adequate Ventilation Unusually Tight ConstructionDetermining if You Have a Confined or Unconfined Space AIR for Combustion VentilationDetermining FRESH-AIR Flow for Heater Location Ventilation Air From Outdoors Ventilation AIRVentilation Air From Inside BuildingMinimum Wall and Ceiling Clearances see Figure InstallationInstallation Check GAS TypeMinimum Non-Combustible Material Clearances If Not Using MantelFloor Clearances Mantel ClearancesInstallation Items Needed Installing Heater Base AssemblyConnecting to GAS Supply Checking GAS Connections Pressure Testing gas Supply Piping systemInstalling 9-Volt Battery In Hand- Held Remote Control Unit Volt Battery InstallationPressure Testing Heater Gas Connections Installing 9-Volt Alkaline Battery In ReceiverInstalling Back Log #1 Installing Logs CGD3924PRInstalling Middle Log #1 Installing Logs on Models CGB3924PR and CGB3930PRLighting Instructions For Your Safety Read Before LightingOperating Heater Hand Held Remote Operation Manual Lighting ProcedureTo Turn OFF GAS To Appliance Thermostat Control OperationInspecting Burners Cleaning and MaintenanceObserved Problem Possible Cause Remedy TroubleshootingMaintenance, Gas leak. See Warning statement at Service Hints SpecificationsWiring Diagram Accessories Technical ServiceCGD3924PR Illustrated Parts BreakdownKEY Part Number Description QTY Parts ListCGB3924PR CGB3930PR CGB3924PR Parts Central Replacement PartsParts Under Warranty Parts not Under Warranty104307 Warranty Information