Desa CSBNT, CSPIPT Installing ROD and Screen, Pressure Testing Heater Gas Connections

Page 10

10

INSTALLATION

Checking Gas Connections (Cont.) Installing Rod and Screen

INSTALLATION

Continued

Pressure Testing Heater Gas Connections

1.Open equipment shutoff valve (see Figure 9, page 9).

2.Open main gas valve located on or near gas meter for natural gas or open propane.LP supply tank valve.

3.Make sure control knob of heater is in the OFF position.

4.Check all joints from equipment shutoff valve to control valve (see Figure 10 or 11). Apply noncorrosive leak detection fluid to gas joints. Bubbles forming show a leak.

5.Correct all leaks at once.

6.Light heater (see Operating Heater, page 11). Check all other internal joints for leaks.

7.Turn off heater (see To Turn Off Gas to Appliance, page 11).

INSTALLING ROD AND SCREEN

1.Insert rod through small rings located at top of screen (see Figure 12).

2.From back of stove, insert rod into hole located inside right front of stove as shown in Figure 13.

3.Slip left side of rod down into slot on inside left front of stove (see Figure 13).

Rod

Rings

Control Valve Location

Equipment

Shutoff Valve

Propane/LP

Supply Tank

Figure 12 - Assembling Rod and Screen

 

Slot on Inside Left

Rod with Screen

Hole on Inside Right

Front of Stove

Front of Stove

 

Assembled

 

 

Figure 10 - Checking Gas Joints on Propane/LP Gas Unit

Control Valve Location

Equipment Shutoff Valve

Gas Meter

Figure 13 - Installing Screen Into Stove (View From Back of Stove)

Figure 11 - Checking Gas Joints on Natural Gas Unit

For..com

111487-01C

Image 10
Contents CSBNT, Csbpt CSPBNT, Cspbpt CSPINT, Cspipt What to do if YOU Smell GASTable of Contents Safety InformationProduct Identification Typical Stove Cabinet Model with Comfort Glow Gas Log HeaterLocal Codes Product FeaturesAIR for Combustion and Ventilation Determining if You Have a Confined or Unconfined Space Determining FRESH-AIR Flow for Heater LocationVentilation Air From Inside Building Unpacking InstallationVentilation Air From Outdoors Clearances to Combustibles Vent-Free Operation Only Minimum Wall and Ceiling Clearances see FigureConnecting to GAS Supply Installation Items NeededPressure Testing Gas Supply Piping System Checking GAS ConnectionsInstalling ROD and Screen Pressure Testing Heater Gas ConnectionsOperating Heater Installing LOG SETFor Your Safety Read Before Lighting Lighting InstructionsThermostat Control Operation Manual Lighting ProcedureInspecting Burners To Turn OFF GAS To ApplianceBurner Injector Holder and Pilot AIR Inlet Hole Cleaning MaintenanceMain Burner LogsTroubleshooting Observed Problem Possible Cause RemedyMaintenance, Gas leak. SeeWarning statement at Technical Service SpecificationsReplacement Parts Service Hints AccessoriesIllustrated Parts Breakdown ModelsParts List Description QTYStove Body Models CSB SERIES, Cspb SERIES, and Cspi Series CSB Series Cspb Series Cspi Series Parts Centrals Owners Registration Form Postage Required 111487-01C Warranty Information