American Standard 6068.22X Install Electrical BOX, Assembly Fig, Install Sweat Solder Adapter Fig

Page 4

1 INSTALL ELECTRICAL BOX

ASSEMBLY; Fig. 3

1. Cut a 127x127mm (5"x 5") opening in finished wall for

ELECTRICAL BOX (1) at the deminsion shown in Fig.3.

2. Rotate the 4 MOUNTING TABS (2) flat against the

electrical box. Holding the MOUNTING TABS (2) in

position install the ELECTRICAL BOX (1) into the opening.

Make sure the MOUNTING TABS (2) are behind the wall.

Fig.3 (TOP SPUD FIXTURE ILLUSTRATED)

127mm

2

 

(5)

 

 

127mm

 

 

(5)

 

 

 

T O P

3

Fig. 3a

3. Tighten the the 4 MOUNTING SCREWS (3) until the

ELECTRICAL BOX (1) is almost secure in the wall.

Before tighting fully rest a level at the top edge of the

ELECTRICAL BOX (1) and make sure the box is level,

then tighten fully. Fig. 3a.

4. *Cut a 2" hole for supply to fixture at deminsion shown.

406mm

(16 REF.)

127mm

(5 MAX.)

T O P

1

*FOR HOLE LOCATION OF

SUPPLY ON BACK INLET FIXTURES, REFER TO FIXTURE BEING INSTALLED FOR CORRECT HEIGHT FROM FINISHED FLOOR

2INSTALL SWEAT SOLDER ADAPTER; Fig. 4

CAUTION

Turn water supplies off

before beginning

Fig. 4

T O P

2

 

1

Note: Control stop inlet is 1" IPS. For optional sweat

connection, install Sweat Solder Adapter (1) (Supplied) for 1" copper pipe supply line. Fig. 4.

1.Clean the end of the supply pipe. Push the threaded ADAPTER (1) on until it is seated against the internal stop. Sweat the ADAPTER (1) to the pipe.

2.From behind the wall install the CONTROL STOP (2) to the water supply line with the outlet positioned as required.

3.Support piping as required.

115mm-134mm (4-1/2 TO 5-1/4)

CONTROL

STOP

OUTLET

FILE

CONTROL STOP

DN 25mm

EDGES

(1" I.P.S.)

 

CLEAN & SOLDER

TO ADAPTER (1)

2

403 TO 441mm

(15-7/8 MIN. TO

17-3/8 MAX.)

3FLUSH OUT SUPPLY LINES; Fig. 5

1.Open SUPPLY STOP (1).

3.Turn on water supply to flush line of any debris or sediment.

4.Close SUPPLY STOP (1) and turn off water supply line.

Fig. 5

COUNTER-CLOCKWISE

CLOCKWISE CLOSES

OPENS CONTROL STOP

CONTROL STOP

1

3

M968550 REV. 1.5

Image 4
Contents Installation Instructions Concealed Flushometer For 1-1/2Top or Back Spud BowlsInstallation UnpackingRoughing-in Dimensions Prior to InstallationFollowing items must be installed Recommended Tools FigInstall Electrical BOX Assembly FigInstall Sweat Solder Adapter Fig Flush OUT Supply Lines FigInstall Vacuum Breaker and Flush Connections Fig Consult Code for detailsInstall Flush Valve Fig Connect Flush Valve to Piping FigInstall the Sensor Wire Grommet 15 into Electrical BOX AC PowerConnect Front Panel to Connect Front Panel to Electrical BOX DC Power Battery Fig Install Front Panel FigConnect Override HOSES, AC & DC Power Fig Connect Solenoid Wiring and Power Supply FigUnit #1 Unit #2Unit #3 For AC-VERSIONRemove Front PANEL. For removing front panel Adjust Supply Stop FigSee for instructions Howto SET Detection Range If Required Stand outside of sensor detection aeraTroubleshooting Flow Charts Selectronic