Installation (cont.)
7c | 8 |
White
Neutral
Green
Red
Black
Wiring option 3* | Lift oven into position. |
(connect the white to the incoming neutral, |
|
attach green to suitable ground) |
|
Installation
1314
1
2
Open door completely. Rotate door | Close door. |
hinge to locked position. |
|
9 | 10 |
Push oven straight in. | Attach screws to the side of the framing. |
| Note: Two screws for single ovens, four screws |
| for double ovens (screws not included). |
11 | 12 |
Replace racks. | Replace door. |
*Note: Check local code to see which wiring option should be used when grounding the unit.
Final Preparation
1.Some stainless steel parts may have a protective wrap, which must be peeled off. All stainless steel body parts should be wiped regularly with hot, soapy water at the end of each cooling period and with liquid cleaner designed for this material when soapy water will not do the job. If
2.The interior of the oven should be washed thoroughly with hot, soapy water to remove film residues and installation debris before being used for food preparation, then rinsed and wiped dry. Solutions stronger than soapy water are rarely needed.
14 | 15 |