VERTICAL CONTACT TOASTER
MAINTENANCE
WARNING
Turn the unit off, disconnect the power source and allow the unit to cool down before performing any service or maintenance on the unit.
Maintenance Schedule
DAILY
1.Turn off power to the toaster.
2.When the toaster is cool, follow the procedures under Cleaning the Release Sheet.
3.Remove heat shield and bun chute. Wash in back sink, sanitize and rinse.
4.Wipe down the outside of the toaster with a slightly damp cloth and allow to air dry.
Cleaning the Release Sheet
1.Turn the rocker switch to off, unplug the unit and allow it to cool down.
2.Put on protective gloves. Remove heat shield and release sheet (Figure 7).
3.Wipe release sheet on both sides with a clean, sanitized towel.
4.Remove front and rear conveyor cover assys. (Figure 4). Wipe exterior of conveyor belt with a clean, sanitized towel.
5.Install front and rear cover assys. (Figure 4) then turn toaster on. Count to 10, then turn toaster off. Remove front and rear cover assys. and wipe new section of belt.
6.Install the release sheet by draping it over both sides of the platen with the crease centered directly on the platen (Figure 7).
7.Install the heat shield (Figure 7). The heat shield clips fit over the tip of the platen and retain the release sheet.
IMPORTANT: Make sure heat shield assy. is activat- ing (depressing) the conveyor interlock switch (see Figure 7). The conveyors will not rotate unless the heat shield is in place and interlock switch is acti- vated (depressed).
CAUTION
To prevent damage to the unit, do not use abra- sive cleaners on the release sheet.
Heat Shield
Release Sheet
Platen
Interlock Switch
Figure 7. Removing/Installing Release Sheet
NOTE: Check the release sheet to make sure it is not caught in the conveyor. Additional release sheets can be obtained through your authorized service agency under part no. 7000110 (3 pack) or 7000111 (10 pack).
Conveyor Belts–Removing, Servicing & Replacing
REMOVING THE CONVEYOR BELT
1.Turn the rocker switch to off, unplug the unit and allow it to cool down.
2.Remove the heat shield, front and rear conveyor covers and release sheet (Figure 4).
NOTE: When replacing conveyor belt, it is recom- mended that the release sheet cleaning procedures be performed.
3.Set both compression knobs to: 6 = 7/8” (22.2 mm).
4.Disconnect the conveyor belt by squeezing any two links together and unhooking both ends of one link (Figure 8). A
NOTE: With conveyor belt removed, the tensioner assemblies (4, page 24) and slide rails (40, page 24) can be replaced.
10 | P/N 1010729 Rev. C 05/04 |