7 Level the Unit

8 Install the Unit

Leveling Information

Note: It is recommended that the unit is level.

Installation of the 75R/75WC/75BEV

1. Plug in the power cord.

1.Use a level to check the levelness of the unit from front to back and from side to side. Level should be placed along top edge and side edge as shown (see Figure 19).

Check

Level

Figure 19

2.

Gently push the unit into position. Be careful not to

 

entangle the electrical cord.

3.

Re-check the leveling, from front to back and side to

 

side. Make any necessary adjustments. The unit’s top

 

surface should be approximately 1/8" below the

 

countertop.

Grille Installation

1.Locate and remove the grille screw from the cabinet, using a standard blade screwdriver (or a 1/4" nutdriver). See Figure 21.

.

2.If the unit is not level, adjust the feet on the corners of the unit as necessary (see Figure 20).

Turn Foot to Adjust

Figure 20

3.Check the levelness after each adjustment and repeat the previous steps until the unit is level. Go on to

8 Install the Unit.

Installation Tip

If the room floor is higher than the floor in the cut-out opening, adjust the rear feet to achieve a total unit rear height of 1/8" less than the opening’s rear height. Shorten the unit height in the front by adjusting the front feet. This allows the unit to be gently tipped into the opening. Readjust the front feet to level the unit after it is correctly positioned in the opening.

Grille Screw

Figure 21

2.Remove the control knob by pulling it away from the cabinet.

3.Identify the grille screw hole on the grille itself. It is located toward the top of the middle recessed section of the grille.

02/2005

11

www.U-LineService.com

Image 11
Contents 75R Refrigerator 75WC Wine Captain and 75BEV Beverage Center Follow Safety Precautions ContentsInspection General PrecautionsInspect and Plan Tools/Materials RequiredPrepare Site Exterior CleaningCut-Out Dimensions Door Swing/Clearances Information Product DimensionsBlack and White 75R Units Reversing the DoorStainless 75R Units and All 75WC Units Side-By-Side Installation InstructionsPower Supply Other Site RequirementsDoor Panel Preparation Prepare/Install Door Panel or Prepare RacksDoor Panel Installation Custom 1/4 Thick Door Panel InsertStaining Wood Trim a Different Color Adding a Final Finish Coat to Wood TrimChecking Door Alignment Electrical SpecificationsAdjust Door Prepare Power SupplyLevel the Unit Install the Unit Leveling Information Installation of the 75R/75WC/75BEVGrille Installation Installation TipStart-Up for the First Time Glass Shelf InstallationStart-Up Troubleshooting Initial Start-UpWho to Call Service Information