Servis-Rhino 2409TL manual OPS-L-0007A

Page 60

OPERATION

OPERATION

LOADER BOOM ASSEMBLY

Inspect condition of each arm section weldment

Ensure all pins are in place.

Ensure all bolts and screws are properly installed.

Check condition of bushings at boom pivot points.

Ensure each hydraulic cylinder is installed and retained correctly. Ensure the proper size pins are used to retain the cylinders in place and are secured properly. OPS-L-0005_A

HYDRAULIC LINE INSPECTION

Check for hydraulic leaks along hoses, cylinders and fittings. IMPORTANT: DO NOT use your hands to check for oil leaks. Use a piece of heavy paper or cardboard to check for hydraulic oil leaks.

Inspect the condition of the valve weldment.

Ensure fitting is properly connected

Inspect condition of bushings.

OPS-L-0006_A

BUCKET INSPECTION

Ensure all pins are in place.

Ensure each hydraulic cylinder is installed and retained correctly. Ensure the proper size pins are used to retain the cylinders in place and are secured properly.

Inspect the condition of the bucket lug weldments.

Inspect condition of bushings.

OPS-L-0007_A

Hydraulic Hoses

Bucket Pins

2409TL 01/11

Operation Section 4-14

© 2011 Alamo Group Inc.

Image 60 Contents
2409TL To the Owner/Operator/Dealer Table of Contents Maintenance Section Safety Section Safety General Safety Instructions and Practices2409TL 01/11 Safety Section Operator Safety Instructions and Practices Safety Equipment Operation Safety Instructions and Practices SG-36 Safety Safety SL-33 Safety Safety Transporting Safety Instructions and Practices Maintenance and Service Safety Instructions and Practices Safety Storage and Parking Safety Instructions and Practices Concluding Safety Instructions and PracticesDecal Location QTY Level Description Decal Description Loader Positions 2409TL 01/11 Safety Section Loader Safety Safety Safety Federal Laws and Regulations Introduction Section Introduction Introduction Introduction Before Operating this Machine Page Assembly and Connecting the Loader Section Assembly Assembly Instructions2409TL 01/11 Assembly Section Proper Ballasting and Wheel Spacing Dismounting and Mounting Mid-Mount Loader Mounting LoaderAssembly Attaching Pin on Bucket Dismounting LoaderAssembly Assembling Quick Attach Device Installing Quick Attach Device Connecting Attachment When Connecting an Attachment to the Loader Quick HitchAssembly Operation Section Operation Standard Equipment and Specifications Operator Requirements Operation Personal Protective Equipment PPE Tractor Requirements Rops and Seat BeltTractor Lighting and SMV Emblem Getting On and Off the Tractor Tractor BallastBoarding the Tractor Dismounting the Tractor Starting the Tractor Pre-Operation Inspection and Service Tractor Pre-Operation Inspection/Service Loader Pre-Operation Inspection/ServiceMount Assembly OPS-L-0007A Do not Operate an Unsafe Tractor or Front END Loader Front END Loader PRE-OPERATION Inspection Driving the Tractor and Loader Driving the Tractor and Loader Operating the Tractor and Loader Operation Operation SL-33 Operation Operating the Loader Filling the BucketOperation Lifting the Load Operation Dumping the Bucket Operating with Float Control Loading from a Bank Operation Peeling and Scraping Loading LOW Trucks or Spreaders from a Pile Backfilling Operation Handling Large Heavy Objects Operating Bale Spear Optional Attachment Loader Storage Transporting the Tractor and Implement Operation Transporting on Public Roadways Hauling the Tractor and Implement Troubleshooting Guide Trouble Possible Cause Possible RemedyProblem Possible Cause Remedy Maintenance Section Maintenance 2409TL 01/11 Maintenance Section Adjusting Bucket Level Indicator Lubrication ScheduleDaily Maintenance Cylinder Service Lift and Bucket Cylinder DisassemblyLift and Bucket Cylinder Reassembly StorageMaintenance Proper Torque for Fasteners Maintenance Maintenance Rhino To the OWNER/OPERATOR/DEALER 2409TL