3Com Router 6000 Family
Installation Manual
Chapter 8
Installing B68 Cabinets
3Com Corporation
8-33
If the resistance is larger than five Mohm, you can finish installation. If not, remove all anchor
strip parts, check that the insulation washers are installed and without damage, reinstall, and
measure insulation until the requirement is satisfied.
Figure 8-17 illustrates how to install cabinets on the concrete floor.

8.3.12 Restoring the Floor

Cut the antistatic floor around the cabinets and restore the floor. Figure 8-38 shows how to
restore the floor and Figure 8-39 shows what the site should look like after the floor is restored.
Caution:
You may install the framework of the antistatic floor onto the side supports, as shown
in Figure 8-38.
1) Framework of the antistatic floor 2) Side supports
Figure 8-38 Restoring the antistatic floor