11.0Install Termination

11.1Slide the termination body onto the cable and remove core. Pull while unwinding, counter-clockwise, starting

with the loose end (Figure 15). Make sure the termination body (not the core) is butted up to the edge of the vinyl tape marker previously applied (Figure 15).

NOTE: Once the termination body makes contact over the mastic seal area, there is no need to continue supporting the assembly. DO NOT PUSH OR PULL ON THE TERMINATION ASSEMBLY WHILE UNWINDING THE CORE.

Counter-Clockwise

Vinyl Tape Marker

 

NOTE: The material being removed at this step is mixed polymers

and can be recycled with

waste.

Figure 15

11.2 Connect ground braid to system ground according to standard practice.

Correct Installation of Termination on Wire Shielded Cable

 

Vi nyl Tape

 

 

Marker

Ridge at End of Cable

 

 

 

Ridge at End

Insulation Shield (Semi-Con)

 

 

 

of High-K Tube

 

 

Semi-Con Insulation Shield

Cable

Envioronmental Top

Stress Controlling Compound

Insulation

Seal

Conductor

 

 

High-K Stress

 

 

 

 

Relief Tube

 

12

78-8117-0985-2 Rev C

Page 12
Image 12
3M 7684-S-8 manual Counter-Clockwise