5.0Routing the Duct

4.3Hang weight from strip.

Manual background Release tab

Tab hole Manual background

4.4Remove successful test strips by pulling on release tab

3MOne Pass Mini Fiber Pathway

Note:  Carefully follow safety, health and environmental information given on the container label or the Material Safety Data Sheet for the isopropyl alcohol.

Avoid installing on or immediately above direct heat sources such as radiant heaters, steam pipes, stoves, etc. If unavoidable, install mechanical anchors on both sides of heat source as necessary.

Avoid installing in high humidity or water born environments such as shower stalls, sinks, etc. If unavoidable, install mechanical anchors on both sides of area as necessary. Area must be clean and dry at time of installation and minimum 72 hours following.

For best results, 3M recommends a curing time of 72 hours after installation of the OnePass Mini Fiber Pathway before subjecting it to temperature extremes below 60°F (16°C) or above 100°F (38°C).

5.0Routing the Duct

Test Weight Hang Time

Result

> 60 seconds

PASS – Install

< 60 second

FAIL – Do not install

The path the duct will follow MUST be clean and dry.

Clean all surfaces along the duct installation path with 3MEasy Trap Duster or equivalent prior to installation.

Greasy, slick, or soiled surfaces must be cleaned with isopropyl alcohol or equivalent along the installation path prior to installation.

Recommended air and duct temperature for installation is 60°F–100°F (16°C–38°C).

The adhesive is permanent. Removing the duct after installation may damage the installation surface.

Do not move or reposition the duct once installed. If for some reason the duct needs to be moved, a mechanical anchor is required to secure the duct to the wall on both sides of the section that has been removed.

In the event repair is necessary, the materials needed for repairing the One Pass Mini Fiber Pathway are included in the repair kit, PN 80-6113-8220-3. (See Fiber Repair section for instructions).

The best location is near the ceiling, baseboard and interior corners. Avoid running duct across open areas or diagonally across walls.

Do not remove liner from duct until applying to installation surface including when handling it while applying to wall surface.

Do not contaminate adhesive with dirt or oils. Do not allow the adhesive to come into contact with anything except the installation surface as you remove the liner.