Use the following guidelines to select a suitable location for the unit.

1.Unit is designed for outdoor installation only. Unit must be installed so all electrical components are protected from water.

2.Condenser coils must have an unlimited supply of air.

3.For ground level installation, use a level prefabricated pad or use a level concrete slab. Do not tie the slab to the building foundation.

4.Maintain level within a tolerance of 1/4" maximum across the entire length or width of the unit.

5.Do not locate the unit where the combustion air supply will be exposed to any of the following substances:

Permanent wave solutions

Chlorinated waxes and cleaners

Chlorine-based swimming pool chemicals

Water softening chemicals

Deicing salts or chemicals

Carbon tetrachloride

Halogen-type refrigerants

Cleaning solvents (such as perchloroethylene)

Printing inks, paint removers, varnishes, etc.

Cements and glues

Antistatic fabric softeners for clothes dryers

Masonry acid washing materials

Chlorinated laundry products

Hydrochloric acid

Use of unit as a construction heater during any phase of construction is not recommended. Very low return air temperatures, harmful vapors, and operation of the unit with clogged or misplaced filters will damage the unit. However, if the installation and operating conditions specified below are followed, use of this unit for heating of buildings or structures under construction is permissible:

The vent hood must be installed per these installation instructions.

A room thermostat must control the furnace. The use of fixed jumpers that will provide continuous heating is not allowed.

The return air duct must be provided and sealed to the unit.

Return air temperature must be maintained between 60°F (16°C) and 80°F (27°C).

Air filters must be installed in the system and must be maintained during construction.

Air filters must be replaced upon construction completion.

The input rate and temperature rise must be set per the unit rating plate.

100% outdoor air must be provided for combustion air requirements during construction. Installation of this unit in its intended outdoor location will accomplish this.

The heat exchanger, components, duct system, air filter(s), and evaporator coil must be thoroughly cleaned following final construction cleanup.

Following the final cleaning, all furnace operating conditions (including ignition, input rate, temperature rise, and venting) must be verified according to these instructions.

Exercise care when moving the unit. Do not remove any packaging until the unit is near the place of installation. An accessory lift kit can be purchased to aid in rigging (see Figure 1). Spreaders whose length exceed the largest dimension across the unit must be used across the top of the unit. Recommended spreader length: 3 ton and smaller package units – 44", 3.5 ton and larger units – 54".

Units may also be moved or lifted with a forklift while still in the factory-supplied packaging. The lengths of the forks of the forklift must be a minimum of 42".

Using Accessory Lift KitFigure 1 CAUTION

Before lifting a unit, make sure that the weight is distributed equally on the cables so that it will lift evenly.

 

Using Accessory Lift Kit

Spreaders

 

Lifting Bracket

(Field Supplied)

Accessory

 

 

 

Sheet Metal

 

 

Screw

To avoid possible damage to unit panels from lifting clevis, place packing material between clevis and panels before lifting unit.

Figure 1

506488-01

Issue 1008

Page 3

Page 3
Image 3
Allied Air Enterprises 4PGE manual Location, Using Accessory Lift Kit