5.Steam Damper Air Piston (Flow Control) Operation Adjustment
Although the damper operation was tested and adjusted prior to shipping at 80 psi (5.51 bar), steam damper operation must be checked before the dryer is put into operation. Refer to page 29 for instructions to check steam damper operation. If damper air adjustment is necessary, locate flow control valve and make necessary adjustments as noted below.
I. FIRE SUPPRESSION SYSTEM
BEFORE YOU START!
CHECK LOCAL CODES AND PERMITS
Call your local water company or the proper municipal authority for information regarding local codes.
IMPORTANT: It is your responsibility to have ALL plumbing connections made by a qualified professional to assure that the plumbing installation is adequate and conforms to local, state, and federal regulations or codes.
IMPORTANT: It is the installer’s or owner’s responsibility to see that the necessary or required water, water pressure, pipe size, or connections are provided. Manufacturer assumes no responsibility if the fire suppression system is not connected, installed, or maintained properly.
113344 - 9 | www.amdry.com | 25 |