Bunn AFPO-3 SL manual Vacuum/Supply Pump Tube Installation, SERVICE cont

Models: AFPO-3 SL

1 25
Download 25 pages 51.21 Kb
Page 20
Image 20
VACUUM/SUPPLY PUMP TUBE INSTALLATION

SERVICE (cont.)

VACUUM/SUPPLY PUMP TUBE INSTALLATION

2.Separate the two halves of the pump and carefully remove the tubing from within.

3.Hold the new pump head as shown in Fig. 24, with rollers in the 2, 6, and 10 o’clock positions.

4.Reinstall tubing in the new pump head by wrap- ping the tubing around the rollers as shown in Fig. 24.

5.Insert the slot of the tubing key (supplied), as shown in Fig. 24, on the rotor so the bottom edge of the key is pressing the tubing into the pump head cavity as shown in Fig. 25.

6.Hold the tubing and rotor in the pump head and remove key carefully.

7.Squeeze the pump body and pump heads together simultaneously until pump body and pump head are touching on all sides. Be careful not to pinch the tubing between the pump body and the pump head.

8.Place the new pump body on the rotor shaft.

9.Replace the four thumbscrews to secure the pump to the motor assembly. Finger-tighten only.

ROLLERS

 

 

PUMP

 

HEAD

 

TUBING

 

KEY

 

EXIT

ENTRY

 

PORT

PORT

 

 

FIG. 24 TUBING START POSITION

P1542

 

 

 

ROTOR

 

ROTOR

 

 

SHAFT

 

 

FIG. 25 TUBING LOADED

P1541

 

20

41093 040408

 

Page 20
Image 20
Bunn AFPO-3 SL manual Vacuum/Supply Pump Tube Installation, SERVICE cont