TABLE 4.2: CLEARANCES FROM VENT PIPING TO COMBUSTIBLE CONSTRUCTION

TYPE OF VENT PIPE

PIPE DIRECTION

ENCLOSURE

MINIMUM CLEARANCE

TO COMBUSTIBLE

 

 

 

MATERIAL

60/100mm

VERTICAL OR

ENCLOSED ON ALL FOUR SIDES

0”

CONCENTRIC VENTING

HORIZONTAL

 

 

HEAT FAB SAF-T VENT

 

AT LEAST ONE SIDE OPEN,

 

PROTECH FASNSEAL

VERTICAL OR

1”

COMBUSTIBLE MATERIAL ON A

Z-FLEX Z-VENT III

HORIZONTAL

 

MAXIMUM OF THREE SIDES

 

FLEX-L STAR-34

 

 

 

 

 

 

 

 

 

HEAT FAB SAF-T VENT

 

 

 

PROTECH FASNSEAL

HORIZONTAL OR VERTICAL

ENCLOSED ON ALL FOUR SIDES

2-1/2”

Z-FLEX Z-VENT III

WITH OFFSETS

 

 

 

FLEX-L STAR-34

 

 

 

 

 

 

 

HEAT FAB SAF-T VENT

 

 

 

PROTECH FASNSEAL

VERTICAL WITH NO OFFSETS

ENCLOSED ON ALL FOUR SIDES

2-1/2”

Z-FLEX Z-VENT III

 

 

 

 

FLEX-L STAR-34

 

 

 

 

 

 

 

6

Page 6
Image 6
Burnham 101008-01R1-2/07 manual Clearances from Vent Piping to Combustible Construction