W I R I N G

ON/OFF SWITCH POWER WIRING

NOTES:

Before running power wiring refer to wiring specifications on previous page for correct wire gauges.

Secure all electrical power connections inside the disconnect switch electrical box. Refer to electrical wiring diagram on pages 30 and 31.

On/Off Switch

Cover

Wire Nut Connections (see instructions)

Power Wiring

Conduit

SINGLE PHASE

All single phase 115V/230V operators will have the following:

L1 WHITE

L2 BLACK

GROUND, GREEN

IMPORTANT NOTE: On three phase operators, power connections must be properly phased. If phased incorrectly, the gate operator will run reversed. To correct this situation, shut off power at main power source and at the operators electrical disconnect switch.

Then reverse any two of the three power leads.

REMOTELY MOUNTED STOP/RESET CONTROL WIRING (REQUIRED)

This control will function as a Stop/Reset command and is to be wired within line of sight of the gate.

Wire Stop/Reset control station to terminals 3 and 5 on the control box on the operator. Make sure that all Stop/Reset controls are wired in series.

THREE PHASE

All three phase operators will have the following:

L1 BLACK

L2 BLACK

L3 BLACK

GROUND, GREEN

1 2 3 4 5 6 7

Control

Conduit

Control

1 2 3

Conduit

 

Stop/Reset

Stop/Reset Button

Button

13