W I R I N G
ON/OFF SWITCH POWER WIRING
NOTES:
Before running power wiring refer to wiring specifications on previous page for correct wire gauges.
Secure all electrical power connections inside the disconnect switch electrical box. Refer to electrical wiring diagram on pages 30 and 31.
On/Off Switch
Cover
Wire Nut Connections
(see instructions)
Power Wiring
Conduit
SINGLE PHASE
All single phase 115V/230V operators will have the following:
•L1 WHITE
•L2 BLACK
•GROUND, GREEN
IMPORTANT NOTE: On three phase operators, power connections must be properly phased. If phased incorrectly, the gate operator will run reversed. To correct this situation, shut off power at main power source and at the operators electrical disconnect switch.
Then reverse any two of the three power leads.
REMOTELY MOUNTED STOP/RESET CONTROL WIRING (REQUIRED)
•This control will function as a Stop/Reset command and is to be wired within line of sight of the gate.
•Wire Stop/Reset control station to terminals 3 and 5 on the control box on the operator. Make sure that all Stop/Reset controls are wired in series.
THREE PHASE
All three phase operators will have the following:
•L1 BLACK
•L2 BLACK
•L3 BLACK
•GROUND, GREEN
1 2 3 4 5 6 7
Control
Conduit
Control | 1 2 3 |
Conduit |
|
Stop/Reset
Stop/Reset Button
Button
13