Site-Planning Checklist
Tab l e 2-2 Site-Planning Checklist
Task N o. Planning Activity Verified by Time Date
1Space evaluation:
• Space and layout
• Floor covering
• Impact and vibration
• Lighting
• Maintenance access
2Environmental evaluation:
• Ambient temperature
• Humidity
• Altitude
• Atmospheric contamination
• Airflow
3Power evaluation:
• Input power type
• Receptacle proximity to the equipment
• Dedicated (separate) circuits for redundant
power supplies
• UPS for power failures
4Grounding evaluation:
• Circuit breaker size
5Cable and interface equipment evaluation:
• Cable type
• Connector type
• Cable distance limitations
• Interface equipment (transceivers)
6EMI evaluation:
• Distance limitations for signaling
• Site wiring
• RFI levels