Normal Operation To Start Heating
1Determine what the HTC’s setpoint must be for your process and material.
2Make sure there is material in the hopper.
3Start the dryer or process blower to begin air flow. Set the proper flow on
the blower if equipped.
4Turn on the main power to the HTC.Make sure the HTC’s disconnect dial
is in the ON position. This powers up the control and the display lights will
illuminate.
5Set the drying temperature. Press the Adjust Setpoint ort buttons to
select the temperature.
7Turn the heater switch to “Enable”to start heating.
ON
O OFF
Heaters
Startup /
Shutdown
For Startup:
1. With heaters in
Standby, turn on
blower or dryer.
2. Enable heaters.
For Shutdown:
1. Switch heaters to
Standby. 
2. Wait 60 seconds
before turning off
blower or dryer.
Enable
Standby
Setpoint Adjust
Buttons
4-24 l Operation