2 weeks after startup

1.Belt tension should be checked after the first 2 weeks of fan operation. Belts tend to stretch and settle into pulleys after an initial start-up sequence. Do not tension belts by changing the setting of the motor pulley, this will change the fan speed and may damage the motor. To re- tension belts, turn the power to the fan motor OFF. Loosen the fasteners that hold the blower scroll plate to the blower. Rotate the motor to the left or right to adjust the belt tension. Belt tension should be adjusted to allow 1/64” of deflection per inch of belt span. Exercise extreme care when adjusting V-belts as not to misalign pulleys. Any misalignment will cause a sharp reduction in belt life and produce squeaky noises. Over-tightening will cause excessive belt and bearing wear as well as noise. Too little tension will cause slippage at startup and uneven wear.

Whenever belts are removed or installed, never force belts over pulleys without loosening motor first to relieve belt tension. When replacing belts, use the same type as supplied by the manufacturer. On units shipped with double groove pulleys, matched belts should always be used.

2.All fasteners should be checked for tightness each time maintenance checks are preformed prior to restarting unit.

Every 3 months

1.Belt tension should be checked quarterly. See instructions in the previous maintenance section. Over-tightening will cause excessive bearing wear and noise. Too little tension will cause slippage at startup and uneven wear.

2.Filters need to be cleaned and/or replaced quarterly, and more often in severe conditions. Washable filters can be washed in warm soapy water. When re-installing filters, be sure to install with the airflow in the correct direction as indicated on the filter.

Filter Quantity Chart

Intake

16” x 20”

20” x 25”

Size 1 Sloped

3

 

Size 2 Sloped

 

3

Size 3 Sloped

6

 

Size 4 Sloped

10

 

Size 5 Sloped

 

8

Size 1 V-Bank

 

3

Size 2 V-Bank

8

 

Size 3 V-Bank

 

8

Size 4 V-Bank

15

 

Size 5 V-Bank

 

12

Yearly

1.Inspect bearings for wear and deterioration. Replace if necessary.

2.Inspect belt wear and replace torn or worn belts.

3.Inspect bolts and set screws for tightness. Tighten as necessary.

4.Inspect motor for cleanliness. Clean exterior surfaces only. Remove dust and grease from the motor housing to ensure proper motor cooling. Remove dirt and grease from the wheel and housing to prevent imbalance and damage.

5.Check for gas leaks and repair if present.

6.Clean flame sensor by rubbing with steel wool to remove any rust build-up,

7.Clean burner with a wire brush and insure burner ports are free of debris. Then wipe the burner with a clean rag.

Burner Orifice

Drill Size

Orifice

Drill Size

Gas Port

31

Air Port

43

27

Page 27
Image 27
Energy Tech Laboratories Modular Direct Fired Heaters Weeks after startup, Every 3 months, Yearly, Filter Quantity Chart

Modular Direct Fired Heaters specifications

Energy Tech Laboratories has established itself as a leader in the development of innovative modular direct fired heaters, designed to meet the evolving demands of industries that require efficient and effective heating solutions. These heaters are engineered to offer versatility, reliability, and enhanced performance, making them suitable for a broad range of applications.

One of the standout features of Energy Tech Laboratories' modular direct fired heaters is their modular design. This allows for easy scalability and customization, enabling users to adjust the heating capacity according to specific requirements. The modular aspect also facilitates straightforward installation and maintenance, reducing downtime and operational costs.

The heaters utilize advanced combustion technology that optimizes fuel consumption while minimizing emissions. This ensures not only a cost-effective operation but also compliance with environmental regulations. By combining high thermal efficiency with a low carbon footprint, these heaters contribute to sustainable energy practices.

In addition to their efficient combustion system, Energy Tech Laboratories incorporates state-of-the-art control technologies in their heaters. These systems allow for precise temperature regulation and can be integrated with existing Building Management Systems (BMS) for enhanced monitoring and control. Users can benefit from real-time data and analytics, which help in diagnosing potential issues and optimizing performance.

Durability is another characteristic that sets these heaters apart. Constructed with high-quality materials, they are designed to withstand harsh industrial conditions, ensuring a long service life. The robust design minimizes the likelihood of breakdowns, which is critical for industries that rely on continuous operation.

Moreover, Energy Tech Laboratories emphasizes safety in the design of their modular direct fired heaters. Equipped with multiple safety features such as flame detection, gas leak detection, and emergency shutdown systems, these heaters are built to operate within stringent safety standards.

The flexibility of these heaters makes them suitable for various sectors, including oil and gas, manufacturing, and construction. Their ability to provide direct heat quickly and efficiently makes them ideal for processes that require consistent temperature control.

In conclusion, Energy Tech Laboratories' modular direct fired heaters represent an advanced solution for today’s energy needs. With their modular design, advanced combustion technologies, and focus on safety and durability, these heaters stand out as a preferred choice for industries seeking reliable and efficient heating solutions. Their commitment to innovation and sustainability positions them as a front-runner in the energy technology sector.