Initial Installation
QUALIFIED INSTALLERS ONLY
TERMINATION:
The bottom of the vent cap shall extend at least 2 feet (0.61 m) above the highest point of the roof where it passes through and at least 2 feet (0.61 m) higher than any portion of the roof within a horizontal distance of 10 feet (3.1 m).
See vent manufacturer’s instructions for vent system clearances to combustibles and vent terminal clearance from roof.
������ ����� ����
������� ������ ����
������������
�� �� ����� ��� |
��� ���� ���
�������
� �� ���� ���
�������
Figure 3: Height of Vertical Termination.
INSTALLATION INTO AN EXISTING CHIMNEY:
This basic venting configuration shown are rough guidelines only. Follow national and local codes for other installation options.
Measure the height of the chimney beforehand and purchase the appropriate kit. Never attempt to over stretch a flexible liner to accommodate the height of the chimney.
• Any flue damper must be removed or locked permanently in the open position.
•The chimney must be clean, in good working order and constructed out of
• Make sure that all chimney
• Make all gas connections and check for leaks.
See vent manufacturer’s instructions for vent system clearances to combustibles and vent terminal clearance from roof.
Figure 4: Installation into an existing chimney.
7