Setup
Setup
Assembling Discharge Deflector to OCDWB01
Insert the rod through the first tab on the gate link frame, discharge deflector, and second tab on the gate link frame (Figure 2). Orient and install the spring so that the loop will rest in the notch on the discharge deflector. Continue to push the rod into the linkage cover. Orient and install the hairpins into the ends of the rod as shown in Figure 2.
Figure 2
1. | Hairpin | 6. | Second tab |
2. | Rod | 7. | Linkage cover |
3. | Discharge deflector | 8. | Spring |
4. | Gate link frame | 9. | Notch |
5.First tab
Figure 3
1.Knock out tab
1.Flip up the existing discharge deflector.
Important: The OCDWB01 comes with its own discharge deflector. When using the OCDWB01, Exmark recommends the original discharge deflector to remain installed on the unit and in the flipped up position. There are some instances where the existing discharge deflector must be removed when installing the OCDWB01. If the original discharge deflector is removed during the OCDWB01 installation, retain the discharge deflector and its hardware for reinstallation once the OCDWB01 is removed.
2.Install the OCDWB01 assembly by inserting the mounting pin into the tube welded to the rear corner of the deck (see Figure 4).
Installing OCDWB01 on Mower Deck
For 32 inch, 36 inch, or Vantage decks: Use a hammer and chisel to knock out the tab, as shown in Figure 3, before starting the installation instructions. Knocking out the tab allows the OCDWB01 frame to fit properly to these decks.
Figure 4
1. | Flip up discharge chute | 3. | OCDWB01 assembly |
2. | Mounting pin inserted | 4. | Rotate |
| into deck tube |
|
|
3.Pivot the assembly towards the deck. The front pin should engage into the slot in the deck as shown in Figure 5.
8