Installation

Installation

Warming Drawer

Provide

Cabinet

Support

2"x 4" or Equivalent Runners

23-1/2"

22"

27"

2"x 4" or Equivalent Runners

23-1/2"

25"

30"

IMPORTANT: When installed below a single or double oven, check to be sure that any oven supports above the cutout do not obstruct the 23-1/2” required depth of the warming drawer cutout.

A 2" min. clearance between oven and warming drawer cutouts are required. Additional clearance may be required if

2 x 4 blocks are used to support runners or solid floor of the oven above.

The warmer drawer may be supported by either a solid bottom, 2 x 4 or 2 x 2 runners.

The support must be level and rigidly mounted, flush with the bottom edge of the cutout.

There is no way to level the drawer once it has been installed. Be sure supports are level.

The entire weight of the drawer is supported by the runners or solid floor and must be capable of supporting 150 lbs.

Step 1

Install

Anti-Tip

Brackets

WARNING:

ANTI-TIP PRECAUTIONS

An anti-tip brace must be installed to prevent the drawer from tipping forward when opened and loaded. Failure to do so could result in personal injury.

PRÉCAUTIONS :

CONTRE LE BASCULEMENT

 

 

 

 

 

 

 

 

 

 

Install

 

 

 

 

 

 

 

 

 

 

2x4 or 2x2

 

 

 

 

 

 

 

 

 

 

Anti-Tip Block

 

 

 

 

 

 

 

 

 

 

Against Rear

 

 

 

 

 

 

 

 

 

 

Cabinet Wall

9"

 

 

 

 

9" From Floor

 

 

 

 

 

 

 

 

 

 

to Bottom

 

 

 

 

 

 

 

 

 

 

of Block

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2x4 or 2x2

 

 

 

 

 

Runners or Solid

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Bottom

 

Pour éviter les blessures, il faut installer une patte de retenue pour empêcher le tiroir de basculer quand il est ouvert et plein.

Step 2

Install

Warming

Drawer

Slide left corner of the drawer into the opening.

Push power cord into the hole leading to the outlet location. Thread the cord through as drawer is being pushed back into the opening. Check to be sure power cord does not get trapped under the drawer.

If the outlet is installed inside the opening, plug the cord into the outlet. In this location, the excess power cord length should be coiled and taped to the right side of the unit.

Push the drawer back until the front flange is flush to the cabinet front.

Open the drawer fully.

Drill pilot holes through the holes in the overlaping frame, one on each corner.

Drive wood screws provided into each corner.