Electrical

Electrical

Requirements

Connect Main Power

All electrical wiring must be completed by a qualified electrician and comply with all local codes and regula- tions.

Enclose all cables routed in the spray booth and high traffic areas in conduit to prevent damage from paint, solvent, and traffic.

NOTE: All options ordered on the ProControl system are electrically tested at the factory.

The ProControl operates with 85-250 VAC, 50/60 Hz input power, with a maximum of 2 amp current draw. The power supply circuit must be protected with a 15 amp maximum circuit breaker.

Not included with system:

Power supply cord compatible to your local power configuration. Wire gauge size must be 8-14 AWG.

The input power access port is 22.4 mm (0.88 in.) diameter. It accepts a bulkhead strain relief fitting or conduit. See FIG. 10.

1.Provide power to the EasyKey. Install a bulkhead strain relief or conduit bulkhead through the

EasyKey port . See FIG. 10.

2.See FIG. 9 and the System Electrical Schematic on page 30 for the L1, N, and ground wiring connec- tions inside the EasyKey.

3.Ground the EasyKey to a true earth ground. See Grounding, page 27.

Input Power

 

Terminal Block

TI13349a

FIG. 9. Main Power Connection